Spain's data centre decree faces court challenges from Madrid and industry groups

Madrid's regional government and the data centre association SpainDC both plan court challenges to the royal decree approved on 20 November. The government defended the text on Monday, 23 November, saying it keeps Spain attractive to investors.

AI text based on reports by ABC TU DIARIO EN ESPAÑOL, eldiario.es, europa press and other publishers. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Madrid, Olivenza · Spain
How it came to this
  1. 20 NovCouncil of Ministers approves the royal decree on data centres
  2. 23 NovMadrid, SpainDC and Castilla-La Mancha criticise the decree while Cuerpo defends it

Decree approved and defended

The Council of Ministers approved the royal decree regulating data centres in Spain on Friday, 20 November, and the Ministry for Ecological Transition drafted it. On Monday, 23 November, First Vice-President Carlos Cuerpo defended the text in Olivenza (Badajoz), calling it "equilibrado" and arguing that it keeps attracting investment while asking companies to invest under fair conditions for the territory and its workers. Cuerpo said the hearing process gathered more than 600 contributions and that a transitional period will give companies room to adjust. He warned that new facilities must not raise electricity prices or make grid access harder for other industries and consumers, citing problems in Ireland and Dublin. El Periódico reports that the final text softened some of the environmental demands included in the first draft.

Madrid moves to the courts

Madrid's regional councillor for digitalisation, Miguel López-Valverde, criticised the government on the same day, saying it wanted to pass the cost of its energy policy onto companies. He said the sanctions regime allows fines of up to six million euros for failing to meet energy and water sustainability criteria or for not providing required information within the deadlines. The Community of Madrid will challenge the decree in court, request precautionary measures and take the matter to Europe. In his words:

“You cannot aim to make our country a digital benchmark while punishing the companies that want to invest and develop their projects here.”

Miguel López-Valverde

He argued that the text will create legal uncertainty, drive away new investment and lead to cancelled projects in Spain, especially in the Community of Madrid.

Industry turns to the Supreme Court

The SpainDC association, which represents the main data centre operators, held its sixth annual congress in Madrid on Monday, 23 November. Its president, Emilio Díaz, called the decree "profoundly disappointing" and said it effectively bans data centres in Spain. SpainDC is preparing an appeal to the Supreme Court and will seek precautionary measures, and Díaz urged other associations and companies to join the challenge. A manifesto the association launched days earlier has gathered more than 160 endorsements, including APPA Renovables, the wind association AEE, Anese and Adigital. Aelec, whose members include Iberdrola, Endesa and EDP, has also criticised the decree, and its president Marina Serrano attended the congress. Speakers at the event called the rules mistaken, alarmist and discriminatory, and a PwC report presented there concludes that installing 3 gigawatts of data centres could generate up to 80,000 jobs and equal 2% of GDP by 2030. A second report by Wood Mackenzie was also presented at the congress.

Castilla-La Mancha joins the dispute

The president of Castilla-La Mancha, Emiliano García-Page, appeared unexpectedly by video at the SpainDC congress to criticise what he called ideological fanaticism. He said:

“I hope ideological fanaticism does not affect the development of this industry, because data centres are just another industry.”

Emiliano García-Page, president of Castilla-La Mancha

He also praised the sector's efforts to save water and optimise energy use, and his intervention was not on the day's programme. The intervention comes in the middle of the campaign ahead of the 29 November vote, which places the data centre dispute inside a wider break between García-Page and the national government. SpainDC says it will take the decree to the Supreme Court, and the Community of Madrid says it will seek precautionary measures in the courts.