Energy Grid · Madrid
Spain sends revised data centre decree to Council of State, easing green rules
The government sent its revised royal decree to the Council of State on Monday, 26 October. It lifts the threshold from 1 MW to 10 MW and offers up to five years of transition in exchange for accepting automatic grid disconnection.
AI text based on reports by LaSexta, ABC TU DIARIO EN ESPAÑOL, eldiario.es and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
The general obligations now apply to data centres above 10 MW, up from 1 MW in the first draft, after more than 600 objections were filed during consultation.
Facilities above 10 MW must still cover 80% of consumption with renewable power, while PPA minimum length falls from ten to six years and the contract age window grows from 18 to 36 months.
Operators can opt into a transitional regime of up to five years, with 60% peak-hour coverage until 31 December 2028, but must join the SRAP run by Red Eléctrica de España and accept automatic disconnection without payment.
The government aims to approve the decree before the 29 November election, and otherwise plans to seek permission from the Abogacía del Estado to approve it while caretaker.
- 29 NovGeneral election; government aims to approve the decree before this date
- 31 Dec60% peak-hour threshold for the transitional regime ends, 70% applies
- 2031Transitional regime runs until 2031, according to EL PAÍS
What the revised draft changes
The Ministry for the Ecological Transition sent the revised royal decree on data centres to the Council of State on Monday, 26 October, after a consultation period that drew more than 600 objections. The text keeps the core obligations of the first draft but softens several of them. The most visible change is the threshold: facilities with an access capacity above 10 MW now fall under the general obligations, up from 1 MW in the original version. According to La Razón, the ministry argues that installations of this size are the ones with an appreciable impact on available grid capacity and on water and territorial resources. Smaller sites are not fully exempt, since communication and publicity duties still apply from 500 kilowatts of IT capacity.
Renewable supply and contract rules
Facilities above 10 MW must still cover at least 80% of their consumption through self-generation or purchase contracts for renewable electricity generated in Spain. The hour-by-hour matching requirement in the first draft drew the sharpest objections from companies, and the revised text adds a gradual route to meet it. Renewable plants linked to a data centre may now have been commissioned up to 36 months before the facility starts operating, against 18 months in the first draft. The minimum length of long-term renewable purchase contracts, known as PPAs, falls from ten years to six. The draft also introduces flexibility for repowered plants, biomass and biogas plants at the end of their regulatory life, and existing solar plants without a prior PPA, while explicitly allowing storage installations to count toward the targets.
A transitional period tied to grid curtailment
Data centres may opt into a transitional regime of up to five years from the decree's entry into force, with looser requirements. Until 31 December 2028 they need 60% renewable coverage, and only in peak hours at their voltage level. After that date, and until the transitional period ends, the requirement rises to 70% in both peak and flat hours. In exchange, these facilities must join the Automatic Power Reduction System (SRAP), a mechanism operated by Red Eléctrica de España that cuts or reduces generation, pumped-storage or storage installations when the grid shows congestion or a real-time fault. Under this regime the grid operator can disconnect the centres automatically when needed, without payment, making them the first category to be cut. The government's argument is that a new entrant should bear the cost of the demand it adds, since flat, constant consumption can deepen the load in evening peak hours.
Industry pushback and the CNMC report
The first draft provoked strong rejection from the sector, and according to La Razón, objections also came from the electricity and telecommunications industries and from the SpainDC employers' group. The National Markets and Competition Commission (CNMC) issued a critical report asking for some obligations to be moderated, and the revised text eases the hourly renewable requirement that the regulator had asked to relax. EL PAÍS reports that companies including Amazon, Microsoft, Google, ACS and Merlin Properties were among those opposing the draft, and that some had threatened multimillion-euro claims and a halt to investment. The ministry says the text keeps the ambition of the original proposal, with the aim of preventing data centre growth from pushing up household and industrial electricity bills.
Timing before the 29 November election
The government wants to approve the decree before the general election on 29 November, a goal El Periódico says it has kept. After the vote, a caretaker government may not approve royal decrees unless they are urgent or clearly serve the general interest. If the decree is not approved in time, Moncloa intends to ask the State Attorney's Office (Abogacía del Estado) for permission to approve it while still in a caretaker role. The draft is now with the Council of State for review. The key dates reported in the coverage are shown below.
Ask about this text
Sources and context
- LaSextaThe data centre decree maintains its key requirements and gives more room to European AI gigafactoriesEl decreto sobre centros de datos mantiene sus requisitos clave y da más margen a las gigafactorías europeas de IA · original in Spanish
- ABC TU DIARIO EN ESPAÑOLThe government backtracks and softens the requirements for developing data centresEl Gobierno da marcha atrás y suaviza los requisitos para desarrollar centros de datos · original in Spanish
- eldiario.esThe government softens the renewable energy requirement for data centres in exchange for accepting disconnectionsEl Gobierno suaviza la exigencia de renovables a los centros de datos a cambio de aceptar desconexiones · original in Spanish
- La RazónThe government maintains 80% hourly renewable energy for data centresEl Gobierno mantiene el 80% de energía renovable hora a hora para los centros de datos · original in Spanish