Energy Grid · Madrid and Zaragoza

Spain approves data centre decree and 17,142 million euro grid plan to 2030

Spain's Council of Ministers approved on Friday, 20 November, a royal decree regulating data centres and an electricity grid plan to 2030 worth 17,142 million euros. The government says the rules avoid a rise of about 5,000 million euros in consumer bills, while critics say the transition period weakens them.

AI text based on reports by europa press, El Periódico, RTVE.es and other publishers. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Madrid, Zaragoza · Spain

Data centre decree approved

The Council of Ministers approved on Friday, 20 November, a royal decree regulating data centres in Spain. The Ministry for the Ecological Transition and the Demographic Challenge drove the rule together with the ministry for economy and digital transformation, and the government presents it as the closing step of this regulatory framework before the general election on 29 November. The decree requires that 80% of the energy a centre consumes comes from new renewable sources in every hourly period, a rule the first draft applied without exceptions.

The final text adds a transition period for projects already under way. Until 31 December 2028 they may source 60% of their consumption from renewables, rising to 70% in 2029 and reaching 80% in 2032. Centres that opt into the transition period can be disconnected when the grid is under strain. Asked about the arrangement, Aagesen rejected the idea that it amounts to a freeze on the sector.

“It is not a moratorium.”

Sara Aagesen

The ministry estimates savings of about 5,000 million euros on citizens' bills and 25% for industry. All centres must hold an energy label A, and water use is capped at 0.1 litres per kilowatt, while energy conditions vary by climate zone.

Renewable share of data centre energy use during transition%
To 31 December 2028
60 %
2029
70 %
2032
80 %

Data from the article text

Critics in the sector and in Aragón

Ecologistas en Acción called the decree a first step toward controlling data centre impacts, but said the transitional regime partly undermines its aim. The group also accused SpainDC, the association of data centre developers in Spain, of pressing to stall the rules. In Aragón, economy councillor Eva Valle said the regional government had not seen the final text and had asked for the Council of State report, which had not yet arrived.

Valle said the requirements are such that none of the projects in Aragón meets them.

“Son unos requisitos que no cumple ninguno de los proyectos que tenemos en Aragón”

Eva Valle

She warned that investors could leave the region and the country, and criticised approval before the election rather than after it. Rafael Benjumea, president of the solar employers' body UNEF, told ABC the decree was rushed during an electoral period and drawn up without analysing alternative technical options, while agreeing that data centre demand needs regulating.

Electricity grid plan to 2030

The Council also approved the electricity planning with a 2030 horizon, worth 17,142 million euros, almost three years after its processing began in December 2023. According to the document, 26% of that investment goes to existing or previously planned initiatives. The so-called starting grid accounts for 4,460 million euros, 2,010 million euros fund interconnections with France, Portugal, Andorra and Morocco, and more than 10,000 million euros go to new actions.

Electricity grid planning to 2030 by componentmillion euros
Total planning
17142 million euros
Starting grid
4460 million euros
Interconnections with France, Portugal, Andorra and Morocco
2010 million euros

Data from the article text

Red Eléctrica will execute the plan, but the government decides which works go ahead and where. Valle was sceptical of the plan, noting that 43% of the works in the previous electricity planning in Aragón were never carried out.

Wind, gas bills and storage rules

The royal decree amends five existing regulations, largely derived from Royal Decree-Law 7/2026, the first measure in the Comprehensive Plan for Response to the Middle East Crisis. Wind farms more than 15 years old can request up to 25% more grid capacity than they were already granted, on nodes reserved for tenders. Capacity is also freed for industrial self-consumption linked to manufacturing, hydrogen and renewable gas. Pumped hydro plants may add power electronics, and solar thermal plants may expand their solar field and add thermal storage. Gas bills must show the origin of the gas supplied, including the renewable share, and carry a QR code linked to the CNMC energy offer comparator. The Council also approved transposing the new EU emissions trading scheme for buildings and road transport.