Transport · Galați and Brăila
Stolen bridge cables push Galați-Brăila expressway opening into 2027
Police in Galați have opened a theft case over stay cables and fixing parts taken from the Siret bridge site. CNAIR says the road, 99% complete, will not open in 2026 because the builder cannot bring replacement parts this year.
AI text based on reports by Stirile ProTV, Mediafax.ro, G4Media.ro and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Police opened a theft case after the builder reported missing stay cable fixings and auxiliary parts in July 2026, with thefts believed to date from late 2025.
CNAIR says the builder cannot bring the stolen stay cables in 2026, and only 64 of 96 planned cables were installed by early November according to Ministry of Transport data.
The 99% complete road was expected to open in December, but CNAIR now expects March or April 2027. The contract is worth 449.42 million lei without VAT.
- Early November 2026Ministry data show 64 of 96 stay cables installed
- 26 November 2026Police confirm the theft investigation publicly
- Spring 2027Expected opening, most likely in March or April
Theft on the bridge site
Police in Galați have opened a criminal case for theft after several stay cable fixing elements and auxiliary components were taken from the construction site of the bridge over the Siret river, part of the Galați-Brăila expressway (DEx6). The Galați county police inspectorate, IPJ Galați, said the thefts are believed to have happened between late 2025 and July 2026, when the builder alerted Section 3 of the Galați police. Investigators are now working to identify those involved and to establish the circumstances. The expressway is 10.76 kilometres long, with two lanes in each direction, three bridges, two viaducts and an underpass.
Works stop until replacement parts arrive
The national road agency CNAIR says the expressway is 99% complete, but the bridge cannot be finished without its stay cables, which carry the deck. Spokesman Alin Șerbănescu told Adevărul that the builder has said it cannot bring the stolen parts in 2026.
“We spoke with the builder. From what they told us, they will not manage to bring this year the stay cables and the fixing elements that were stolen.”
Şerbănescu added that deck slabs cannot be laid or concreted until the cables are in place, although the crew can keep working on the metal structures through the winter. Ministry of Transport data from early November showed 64 of the 96 planned stay cables and 32 of the 204 deck slabs installed. The bridge over the Siret is 307 metres long, and the whole bridge complex on the route is 1.79 kilometres.
- Stay cables installed
- 64
- Stay cables planned
- 96
- Deck slabs installed
- 32
- Deck slabs planned
- 204
Data from the article text
Repeated thefts and the builder's complaint
The builder, an association of firms from the UMB group controlled by businessman Dorinel Umbrărescu, filed the complaint with police. CNAIR says the first major theft was flagged roughly two months before its spokesman spoke to the press, and that more parts disappeared afterwards. Police date the builder's report to July 2026. The spokesman said the builder had a security firm at the site, or previously did, and that the builder must clarify matters with both police and that firm. He called the losses a national loss and noted that the thieves could also have benefited from the new infrastructure.
Cost, timetable and risks
The contract is worth 449.42 million lei without VAT, according to CNAIR data published in August, and is financed through the Transport Programme 2021-2027. It was awarded to an association of Spedition UMB, Tehnostrade and SA&PE Construct. The transport minister had announced an inauguration in December, but CNAIR now expects the road to open in spring 2027, most likely in March or April.
The spokesman also warned about the structure itself:
“If you do not have the stay cables, the bridge risks collapsing.”
Ask about this text
Sources and context
- Stirile ProTVTheft at the construction site of the bridge over the Siret, on the Galați-Brăila expressway. Police have opened a criminal caseFurt pe şantierul podului peste Siret, de pe Drumul Expres Galaţi-Brăila. Poliţiştii au deschis un dosar penal · original in Romanian
- Mediafax.roThey stole the components of a bridge and blocked the inauguration of an entire expressway. Drivers have to wait until 2027Au furat componentele unui pod și au blocat inaugurarea unui întreg drum expres. Șoferii mai au de așteptat până în 2027 · original in Romanian
- Mediafax.roPolice confirm the theft of parts from the bridge over the Siret. How much will the inauguration of the section near Galați be delayedPolițiștii confirmă furtul pieselor din podul peste Siret. Cu cât va fi amânată inaugurarea tronsonului de lângă Galați · original in Romanian
- G4Media.roSteel cables of the bridge over the Siret were stolen / Inauguration of the Brăila - Galați expressway postponed to 2027 / Bridge is 99% completeS-au furat cablurile de oțel ale podului peste Siret / Inaugurarea drumului expres Brăila - Galați, amânată pentru 2027 / Podul e finalizat în proporție de 99% · original in Romanian