Transport · Galați and Brăila

Stolen bridge cables push Galați-Brăila expressway opening into 2027

Police in Galați have opened a theft case over stay cables and fixing parts taken from the Siret bridge site. CNAIR says the road, 99% complete, will not open in 2026 because the builder cannot bring replacement parts this year.

AI text based on reports by Stirile ProTV, Mediafax.ro, G4Media.ro and other publishers. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Galați, Brăila · Romania
How it came to this
  1. Early November 2026Ministry data show 64 of 96 stay cables installed
  2. 26 November 2026Police confirm the theft investigation publicly
  3. Spring 2027Expected opening, most likely in March or April

Theft on the bridge site

Police in Galați have opened a criminal case for theft after several stay cable fixing elements and auxiliary components were taken from the construction site of the bridge over the Siret river, part of the Galați-Brăila expressway (DEx6). The Galați county police inspectorate, IPJ Galați, said the thefts are believed to have happened between late 2025 and July 2026, when the builder alerted Section 3 of the Galați police. Investigators are now working to identify those involved and to establish the circumstances. The expressway is 10.76 kilometres long, with two lanes in each direction, three bridges, two viaducts and an underpass.

Works stop until replacement parts arrive

The national road agency CNAIR says the expressway is 99% complete, but the bridge cannot be finished without its stay cables, which carry the deck. Spokesman Alin Șerbănescu told Adevărul that the builder has said it cannot bring the stolen parts in 2026.

“We spoke with the builder. From what they told us, they will not manage to bring this year the stay cables and the fixing elements that were stolen.”

Alin Șerbănescu

Şerbănescu added that deck slabs cannot be laid or concreted until the cables are in place, although the crew can keep working on the metal structures through the winter. Ministry of Transport data from early November showed 64 of the 96 planned stay cables and 32 of the 204 deck slabs installed. The bridge over the Siret is 307 metres long, and the whole bridge complex on the route is 1.79 kilometres.

Bridge components installed, early November 2026 (Ministry of Transport)
Stay cables installed
64
Stay cables planned
96
Deck slabs installed
32
Deck slabs planned
204

Data from the article text

Repeated thefts and the builder's complaint

The builder, an association of firms from the UMB group controlled by businessman Dorinel Umbrărescu, filed the complaint with police. CNAIR says the first major theft was flagged roughly two months before its spokesman spoke to the press, and that more parts disappeared afterwards. Police date the builder's report to July 2026. The spokesman said the builder had a security firm at the site, or previously did, and that the builder must clarify matters with both police and that firm. He called the losses a national loss and noted that the thieves could also have benefited from the new infrastructure.

Cost, timetable and risks

The contract is worth 449.42 million lei without VAT, according to CNAIR data published in August, and is financed through the Transport Programme 2021-2027. It was awarded to an association of Spedition UMB, Tehnostrade and SA&PE Construct. The transport minister had announced an inauguration in December, but CNAIR now expects the road to open in spring 2027, most likely in March or April.

The spokesman also warned about the structure itself:

“If you do not have the stay cables, the bridge risks collapsing.”

Alin Șerbănescu