Transport · Bacău, Roman, and Pașcani
30 more km of Romania's A7 motorway due by year-end, Pașcani link in 2027
Transport Minister Ștefan Ovidiu Popa said another 30 kilometres of the Moldova Motorway (A7) will open by the end of 2026, while bad weather is slowing works on the Bacău-Pașcani stretch.
AI text based on reports by Digi24, adevarul.ro, Ziare.com and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Transport Minister Ștefan Ovidiu Popa said 30 km more of the Moldova Motorway (A7) will open by the end of 2026, bringing the road to about 290 km between Ploiești and Roman.
CNAIR director general Cristian Pistol said the three Bacău-Pașcani lots, totalling 77 km, stand at 83% on lot 1, 70% on lot 2 and 62% on lot 3.
Popa said works up to Pașcani should be finished in the first part of 2027, while Ionuț Ciurea of Pro Infrastructura said the stretch should have been completed last year.
Popa said the SAFE programme is now operational, allowing design and then construction to start on the 62 km Pașcani-Suceava section.
- May 2023Works on lot 1 begin
- 24 NovMinister announces 30 km more to open by year-end
- First part of 2027Pașcani stretch targeted for completion
A 30 km opening before year-end
Transport Minister Ștefan Ovidiu Popa said on Tuesday, 24 November 2026, that another 30 kilometres of the Moldova Motorway (A7) will open to traffic by the end of this year. Once that stretch opens, the road will run about 290 kilometres between Ploiești and Roman, including the Bacău ring road (VO Bacău). During a visit to the sites between Bacău and Mircești, Popa noted that the Romanian contractor UMB is working across all 49 kilometres with more than 1,200 workers and over 800 machines. He posted the announcement on Facebook after the visit. Popa said progress is fast but that unfavourable weather is slowing the Bacău-Pașcani stretch. He estimated that works will realistically be finished as far as Roman Sud, with the rest up to Pașcani due in the first part of 2027.
Progress on the three lots
CNAIR director general Cristian Pistol gave completion figures for the three Bacău-Pașcani lots: 83% on lot 1 (Săucești-Trifești), 70% on lot 2 and 62% on lot 3. Those lots total 77 kilometres, and UMB is mobilised there with more than 1,500 workers and over 900 machines. The Pistol figures cover all 77 kilometres, against the 49 kilometres in Popa's count, so they describe different scopes. For this year, Pistol's target is opening the road from Bacău to Roman, 30 kilometres, with Pașcani following in the first part of 2027. He tied the timetable to two factors.
“The calendar depends on two things: the weather and the financing.”
Pistol said that once the PNRR ends, the remaining works will be paid from the state budget, and that CNAIR has requested the necessary sums. He also said he wants travel possible by next summer from Pașcani to the port of Constanța (605 km), to Tigveni (522 km) and to Craiova (600 km).
- Lot 1 (Săucești-Trifești)
- 83 %
- Lot 2
- 70 %
- Lot 3
- 62 %
Data from the article text
SAFE funding and the Pașcani-Suceava section
Popa said the SAFE programme is now operational, which allows design and then construction to start urgently on the 62 km Pașcani-Suceava section. During the site visit, PSD president Sorin Grindeanu, a former transport minister, said the Moldova Motorway is taking shape up to Pașcani. He praised the builder and the CNAIR representatives for reaching an important stage.
“I think we were in much the same position three years ago, when the contracts were signed and few people truly believed we would build this motorway.”
Grindeanu said the two new lots near Bacău, which were financed through SAFE, are part of a wider network. He said the final result would also include two further portions: the Pașcani node toward Iași-Ungheni and a link toward Suceava-Siret.
Debate over CNAIR and CNIR
During the same visit, Grindeanu turned to the two state companies, CNAIR and CNIR, and told Pistol that Romania needs one company rather than two. He said it is clear that one company doing the work as it has over the years is needed, which expresses his support and is not a merger decision. CNAIR is the renamed CNADNR, under Emergency Ordinance 55/2016, published in the Official Monitor on 28 September 2016. The same ordinance provided for the investment company CNIR, to which some projects under implementation were to be transferred. Gabriel Budescu is director general of CNIR, while Cristian Pistol leads CNAIR.
Criticism of the delays
Ionuț Ciurea, a representative of the Pro Infrastructura association, told HotNews in September that the unfinished works on the A7 should have been ready about a year earlier. Those sections were later promised for the end-of-August PNRR deadline, but at that point the Adjud-Bacău lots opened instead. Ciurea's view was stated in that interview.
“We should have been at Pașcani last year.”
The current timetable therefore puts the Bacău-Roman stretch, 30 kilometres, due by year-end, and the Pașcani section in the first part of 2027.
Ask about this text
Sources and context
- Digi24Transport Minister: Another 30 kilometers of the A7 will be ready by the end of the year. When the section to Pașcani will be readyMinistrul Transporturilor: Încă 30 de kilometri din A7 vor fi gata până la sfârșitul anului. Când va fi gata tronsonul până la Pașcani · original in Romanian
- adevarul.ro“It is clear that we need a single company”. The allusion made by Grindeanu on the A7 construction site in front of the CNAIR head, regarding the merger with CNIR"E clar că avem nevoie de o singură companie". Aluzia făcută de Grindeanu pe șantierul A7 în fața șefului CNAIR, privind comasarea cu CNIR · original in Romanian
- Ziare.comCristian Pistol, about the works on the Moldova Motorway: “I want travel to be possible by next summer from Pașcani to the Port of Constanța, to Tigveni and to Craiova” PHOTOCristian Pistol, despre lucrările pe Autostrada Moldovei: "Vreau ca până vara viitoare să se poată circula de la Pașcani la Portul Constanța, la Tigveni și la Craiova" FOTO · original in Romanian
- HotNews.roVIDEO Which sections of the Moldova Motorway A7 will open by the end of the year: “Unfortunately, the works are slowed down by the weather”VIDEO Ce tronsoane din Autostrada Moldovei A7 se mai deschid până la final de an: "Din păcate, lucrările sunt înregunate de vreme" · original in Romanian
- Sorin Grindeanu
- PSD president and former transport minister who visited the A7 sites