Transport · Bacău, Roman, and Pașcani

30 more km of Romania's A7 motorway due by year-end, Pașcani link in 2027

Transport Minister Ștefan Ovidiu Popa said another 30 kilometres of the Moldova Motorway (A7) will open by the end of 2026, while bad weather is slowing works on the Bacău-Pașcani stretch.

AI text based on reports by Digi24, adevarul.ro, Ziare.com and other publishers. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Bacău, Roman, Pașcani, Ploiești · Romania
How it came to this
  1. May 2023Works on lot 1 begin
  2. 24 NovMinister announces 30 km more to open by year-end
  3. First part of 2027Pașcani stretch targeted for completion

A 30 km opening before year-end

Transport Minister Ștefan Ovidiu Popa said on Tuesday, 24 November 2026, that another 30 kilometres of the Moldova Motorway (A7) will open to traffic by the end of this year. Once that stretch opens, the road will run about 290 kilometres between Ploiești and Roman, including the Bacău ring road (VO Bacău). During a visit to the sites between Bacău and Mircești, Popa noted that the Romanian contractor UMB is working across all 49 kilometres with more than 1,200 workers and over 800 machines. He posted the announcement on Facebook after the visit. Popa said progress is fast but that unfavourable weather is slowing the Bacău-Pașcani stretch. He estimated that works will realistically be finished as far as Roman Sud, with the rest up to Pașcani due in the first part of 2027.

Progress on the three lots

CNAIR director general Cristian Pistol gave completion figures for the three Bacău-Pașcani lots: 83% on lot 1 (Săucești-Trifești), 70% on lot 2 and 62% on lot 3. Those lots total 77 kilometres, and UMB is mobilised there with more than 1,500 workers and over 900 machines. The Pistol figures cover all 77 kilometres, against the 49 kilometres in Popa's count, so they describe different scopes. For this year, Pistol's target is opening the road from Bacău to Roman, 30 kilometres, with Pașcani following in the first part of 2027. He tied the timetable to two factors.

“The calendar depends on two things: the weather and the financing.”

Cristian Pistol

Pistol said that once the PNRR ends, the remaining works will be paid from the state budget, and that CNAIR has requested the necessary sums. He also said he wants travel possible by next summer from Pașcani to the port of Constanța (605 km), to Tigveni (522 km) and to Craiova (600 km).

Completion of Bacău-Pașcani lots, 24 November 2026%
Lot 1 (Săucești-Trifești)
83 %
Lot 2
70 %
Lot 3
62 %

Data from the article text

SAFE funding and the Pașcani-Suceava section

Popa said the SAFE programme is now operational, which allows design and then construction to start urgently on the 62 km Pașcani-Suceava section. During the site visit, PSD president Sorin Grindeanu, a former transport minister, said the Moldova Motorway is taking shape up to Pașcani. He praised the builder and the CNAIR representatives for reaching an important stage.

“I think we were in much the same position three years ago, when the contracts were signed and few people truly believed we would build this motorway.”

Sorin Grindeanu, PSD president and former transport minister

Grindeanu said the two new lots near Bacău, which were financed through SAFE, are part of a wider network. He said the final result would also include two further portions: the Pașcani node toward Iași-Ungheni and a link toward Suceava-Siret.

Debate over CNAIR and CNIR

During the same visit, Grindeanu turned to the two state companies, CNAIR and CNIR, and told Pistol that Romania needs one company rather than two. He said it is clear that one company doing the work as it has over the years is needed, which expresses his support and is not a merger decision. CNAIR is the renamed CNADNR, under Emergency Ordinance 55/2016, published in the Official Monitor on 28 September 2016. The same ordinance provided for the investment company CNIR, to which some projects under implementation were to be transferred. Gabriel Budescu is director general of CNIR, while Cristian Pistol leads CNAIR.

Criticism of the delays

Ionuț Ciurea, a representative of the Pro Infrastructura association, told HotNews in September that the unfinished works on the A7 should have been ready about a year earlier. Those sections were later promised for the end-of-August PNRR deadline, but at that point the Adjud-Bacău lots opened instead. Ciurea's view was stated in that interview.

“We should have been at Pașcani last year.”

Ionuț Ciurea

The current timetable therefore puts the Bacău-Roman stretch, 30 kilometres, due by year-end, and the Pașcani section in the first part of 2027.