Transport · Berlin, Hanover, and Bremen

Deutsche Bahn cuts planned rail corridor renovations to 13 through 2031

Only 13 of 21 planned corridor renovations will go ahead between 2027 and 2031, the transport ministry and Deutsche Bahn said on Friday. The completion date for the full programme is now open, and northwest routes, Bremen-Hamburg and the German side of the Berlin-Szczecin line face later works.

AI text based on reports by www.money.pl, stern.de, Norddeutscher Rundfunk and other publishers. Changed . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Berlin, Hanover, Bremen, Frankfurt · Germany
How it came to this
  1. 2029Hamburg-Hanover, Würzburg-Ansbach-Treuchtlingen and Aachen-Köln
  2. 2030Stendal-Magdeburg and Uelzen-Stendal
  3. 2031Lehrte-Groß Gleidingen and Munich-Rosenheim (second stage)

Fewer renovations, pushed back

Deutsche Bahn and the federal transport ministry said on Friday, 9 October, that only 13 of the planned 21 corridor renovations will be carried out between 2027 and 2031. Corridor renovations are multi-month full closures of busy lines, and the original concept, presented in February 2023, envisaged around 40 such routes. The programme was previously planned to finish by 2036, but the completion date for all routes is now described as completely open. According to the announcement, no corridor renovations are being cancelled, only postponed, and the priority list for 2032 onward will be set next year.

Corridor renovations planned through 2031
Previous plan
21
New plan (2027-2031)
13

Data from the article text

Why the plan was reworked

Transport minister Steffen Bilger (CDU) said the corridor plan was right but that its implementation too often failed to deliver the desired results. Pressure grew from freight competitors and customer associations after the Berlin-Hamburg line, closed for more than nine months, saw its spring reopening postponed by several weeks. Long freight detours without an alternative route added to the criticism, and the Riedbahn between Frankfurt and Mannheim, which started successfully in 2024, was followed by a series of setbacks.

“That is why we are now drawing the consequences from our experience and improving the strategy.”

Steffen Bilger, german federal transport minister

Deutsche Bahn chief Evelyn Palla focused on passengers in the same announcement.

“We want to keep the burdens on our customers during construction work as low as possible.”

Evelyn Palla

The 2027 to 2031 schedule

Three corridors are set for 2027: Lehrte-Berlin, Rosenheim-Salzburg and Fulda-Hanau. The Berlin-Hanover line has been closed for a week and stays shut until December 2027, a 14-month full closure that the detour extends journeys by 80 minutes. In 2028 the list includes Köln-Koblenz, Munich-Rosenheim (first stage), Hagen-Unna-Hamm and Lübeck-Hamburg, while 2029 brings Hamburg-Hanover, Würzburg-Ansbach-Treuchtlingen and Aachen-Köln. Stendal-Magdeburg and Uelzen-Stendal follow in 2030, and Lehrte-Groß Gleidingen and the second stage of Munich-Rosenheim in 2031. The Frankfurt-Heidelberg renovation drops out of the window and moves beyond 2031, having originally been planned for 28 June to 14 December 2030.

Northwest and cross-border effects

The Bremen mobility department said works between Bremen and Bremerhaven will start in 2032 at the earliest, because the construction sector cannot complete all its orders. Gunnar Polzin, head of transport in the Bremen ministry, argued this is still good for the city, since newer signalling technology available from around 2030 will be installed. The Bremen-Hamburg renovation, previously planned from 2031, will now start a year later at the earliest, and the Bremen-Hanover and Bremen-Osnabrück lines are also affected. Passengers in the northwest face at least five more years of delays and cancellations. On the German side of the Berlin-Szczecin line, completion of works between Angermünde and the Polish border has been pushed back by one year to December 2028.

Restart and signalling

After each renovation, service will return in stages, with freight trains first and passenger trains later, and a dedicated commissioning team will handle the transition and fix smaller faults that only appear in operation. Detour routes will be prepared more intensively, and a second freight detour on the Berlin-Hanover route is due to be available from February. Every rebuilt interlocking will be ready for the European ETCS train control system, instead of only selected sections as before. Deutsche Bahn is handling 28,000 construction sites this year, which have caused heavy delays and cancellations across the network, and almost every second long-distance train in Germany arrives late.