Energy Grid · Choczewo, Gdańsk, and Gdynia
Poland approves Baltic pier to supply components for first nuclear plant
Regional environmental authorities in Gdańsk have approved construction of a 1,112-meter Baltic unloading pier to deliver heavy reactor equipment for the Lubiatowo-Kopalino nuclear plant.
AI text based on reports by Dziennik Bałtycki, radiogdansk.pl, www.portalsamorzadowy.pl and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
The Regional Directorate for Environmental Protection in Gdańsk approved the environmental decision on 30 September 2026 for the offshore unloading pier and access road.
The 1,112-meter reinforced concrete pier features a 970-meter marine section designed for roll-on/roll-off platforms and crane systems to unload reactor pressure vessels and steam generators.
The Maritime Office in Gdynia is currently conducting a tender for the contractor while preparing filings for a water permit and companion location decision.
The Westinghouse-Bechtel consortium took over the Lubiatowo-Kopalino site in August 2026, targeting AP1000 reactor commissioning in 2036, 2037, and 2038.
- 2036First AP1000 reactor scheduled to begin commercial operation
- 2037Second reactor scheduled to enter operation
- 2038Third reactor scheduled to enter operation
The Regional Directorate for Environmental Protection in Gdańsk has issued an environmental decision for the Marine Off-loading Facility and an associated technical road. Formally approved on 30 September 2026 and announced on 5 October, the clearance provides the legal and environmental framework for offshore logistics serving Poland's first nuclear power station. The application was submitted jointly by the Maritime Office in Gdynia and state project company Polskie Elektrownie Jądrowe. Developing an offshore unloading pier is intended to relieve regional road and railway networks, allowing outsized structural components to arrive directly by sea.
Deputy Minister of Infrastructure Arkadiusz Marchewka stated that the decision advances strategic marine logistics:
“Obtaining the environmental decision for MOLF brings us closer to delivering infrastructure that will be essential for building Poland's first nuclear power plant. Using maritime transport to deliver the largest and heaviest plant components will allow us to tap into the potential of Polish ports and maritime infrastructure.”
Technical design and marine infrastructure
The planned facility consists of a permanent, openwork reinforced concrete pier resting on steel piles. The entire structure spans approximately 1,112 meters, including an offshore section measuring roughly 970 meters into the Baltic Sea. Engineering specifications state that the pier will accommodate ultra-heavy equipment, including reactor pressure vessels and steam generators. Unloading operations will utilize lift-on/lift-off systems with heavy cranes alongside roll-on/roll-off platforms for specialized transport vehicles. The project scope also encompasses dedicated mooring berths, an approach channel, a turning basin, and a vessel manoeuvring area.
- Total pier length
- 1112 m
- Offshore section
- 970 m
Data from the article text
Environmental requirements and hydrodynamic research
The environmental decision sets strict construction and operational conditions to protect local ecosystems and coastal morphology. Mandatory measures focus on habitat and species preservation, water quality controls, noise limits, and continuous monitoring of coastal erosion. The approval relied on an environmental impact report with biological surveys covering flora, local habitats, and coastal bird migration corridors. Specialized technical analyses incorporated 2025 hydrodynamic and sediment transport modeling conducted by the Institute of Hydro-Engineering of the Polish Academy of Sciences. The Maritime Office in Gdynia reported that decades of accumulated coastal data enabled researchers to assess storm impacts, seasonal variances, and long-term coastal changes against computational models.
Michał Olszewski, vice-president of Polskie Elektrownie Jądrowe, commented on the regulatory progress:
“This is another milestone that allows us to maintain good momentum on our project.”
Permitting pipeline and nuclear plant schedule
The Maritime Office in Gdynia will oversee the construction of the hydrotechnical infrastructure and is currently evaluating contractor bids in an open tender. In the coming days, the office plans to file applications for a companion investment location decision and a water permit before seeking an official building permit. The nuclear power plant is located at the Lubiatowo-Kopalino site within the Choczewo municipality of Pomerania. Polskie Elektrownie Jądrowe submitted its nuclear construction license application to the National Atomic Energy Agency in March 2026. In August 2026, the developer handed the site over to the American consortium of Westinghouse and Bechtel, where deep geological surveys and secondary preparatory works are actively underway. The first Westinghouse AP1000 reactor is scheduled to begin operations in 2036, followed by unit two in 2037 and unit three in 2038.
Ask about this text
Sources and context
- Dziennik BałtyckiStworzą morski punkt rozładunku na potrzeby budowy elektrowni jądrowej. Jest decyzja RDOŚ
- radiogdansk.plDecyzja środowiskowa dla morskiego terminala dla pomorskiej elektrowni jądrowej - Radio Gdańsk
- www.portalsamorzadowy.plNad morzem powstanie ażurowy pomost długi na 1 km. Przypłyną tu ogromne elementy
- wnp.plPomorskie: Jest decyzja środowiskowa dla morskiego terminala na potrzeby elektrowni jądrowej
- Arkadiusz Marchewka
- Deputy Minister of Infrastructure
- Michał Olszewski
- Vice-president of the management board at Polskie Elektrownie Jądrowe