Transport · Bucharest and Otopeni
Magistrala 6 metro to Otopeni airport reaches 80% in south and 36% in north
Transport Minister Ștefan Ovidiu Popa said the southern section of Bucharest's Magistrala 6 metro is 80% complete and the northern stretch toward Otopeni airport is 36% complete. The structural works across the whole line are due in the first part of 2029.
AI text based on reports by Stirile ProTV, Digi24, Ziare.com and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
The 6.6 km section from 1 Mai to Tokyo, with six stations, reached 80% physical progress, and its tunnels from Tokyo to Piața Montreal are finished.
The 7.6 km Tokyo to Otopeni airport stretch, with six stations, stands at 36%, and TBM boring is under way on line 1 between Bruxelles and Paris.
Minister Ștefan Ovidiu Popa said structural works across the full 14.2 km, 12-station line should finish in the first part of 2029.
CNAB launched a tender on 27 November to modernise the Terminal Departures North baggage system, estimated at 36.8 million euro with works of up to 20 months.
Southern section nears completion
Romanian Minister of Transport Ștefan Ovidiu Popa reported good progress on the Magistrala 6 metro in a Facebook post on Thursday, 26 November 2026. The line is designed to bring Bucharest's metro network to Henri Coandă International Airport in Otopeni. Its 14.2 km route with 12 stations is split into two sections, and the southern one, running from 1 Mai to Tokyo, covers 6.6 km and six stations. According to the minister, that stretch has reached 80% physical progress. Both TBM tunnelling machines there are still boring, and the tunnels from Tokyo through Băneasa Airport and Gara Băneasa to Piața Montreal are finished. Work now focuses on two interstations, Expoziției to Pajura on line 2 and Piața Montreal to Expoziției on line 1.
Northern stretch toward Otopeni
The northern section runs 7.6 km from Tokyo to Otopeni airport, with six stations, and it stood at 36% physical progress on the same date. Its TBM machines are already active. On line 1 tunnelling is under way between the Bruxelles and Paris stations, while the line 2 machine is being readied to start the same stretch. The two sections are at very different stages, with the south far ahead of the north.
- Southern section (1 Mai - Tokyo)
- 80 %
- Northern section (Tokyo - Otopeni airport)
- 36 %
Data from the article text
Target date for completion
The minister set the first part of 2029 as the target for the structural works across the whole Magistrala 6 line. He described the project as one of public utility and national interest under Government Decision no. 496/2017, which also contributes to the development of the trans-European transport network. The line is meant to give a direct link to Otopeni airport. The articles give no date for opening the line to passengers. Popa said of the project:
“It is a project awaited for many years, both by Bucharest residents and by residents of northern Ilfov county.”
Baggage system tender at the airport
In a separate press release published on 27 November, the Bucharest National Airports Company (CNAB) launched a tender to modernise the baggage system at the Terminal Departures North of Henri Coandă airport. The contract covers design and execution of the works, plus operation, maintenance and warranty repairs, and its estimated value is 36.8 million euro. CNAB says the works will run for a maximum of 20 months and be staged so that several check-in desks stay open. Baggage processing must stay at a minimum of 50% of the existing system's capacity during the works. Meanwhile the departures south system will run at full capacity. The stated aims are higher baggage handling capacity, shorter processing times and better system reliability. Funding comes from CNAB's own investment sources.
Ask about this text
Sources and context
- Stirile ProTVThe baggage processing system at Henri Coandă Airport will be modernized. How long will the works takeSistemul de procesare a bagajelor de la Aeroportul "Henri Coandă" va fi modernizat. Cât vor dura lucrările · original in Romanian
- Digi24Metro to the airport: what is the status of the works on Magistrala 6. The Minister of Transport announces good progressMetroul spre aeroport: care e stadiul lucrărilor la Magistrala 6. Ministrul Transporturilor anunță "progres bun · original in Romanian
- Ziare.comThe metro line to Otopeni Airport will be ready in 2029, announces the Minister of Transport: A work awaited for many years VIDEOLinia de metrou până la Aeroportul Otopeni va fi gata în 2029, anunță ministrul Transporturilor: "O lucrare așteptată de mulți ani" VIDEO · original in Romanian