Gravas school gas works delayed as over 80% of welds cannot be certified
The Municipality of Athens says gas pipe works at the Gravas school complex will run into December after more than 80% of welds in the large boiler room could not be certified. Students may stay without heating until around 5 December.
AI text based on reports by H Kαθημερινή, NewsIT, Η Ναυτεμπορική and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Over 80% of the welds in the large boiler room's gas piping cannot be certified to current specifications, although none shows a leak. The welds date from the 2003 installation, according to the municipality.
The whole run from the supply point to the boilers, about 100 metres, is being replaced. Works started on Friday, 20 November, and are estimated to take at least 15 days.
Students at the Gravas complex are expected to remain without heating until around 5 December 2026, while works continue until at least early December.
The interventions cost 230,000 euros in total, of which 100,000 euros covers the additional works, according to the municipality.
The smaller boiler room at the 40th Athens Gymnasium passed the ENAON inspection on Friday, 20 November, and its gas supply was switched on. The tightness certificate is still awaited.
- 20 NovReplacement of the about 100-metre pipe run starts
- Early December 2026Works expected to run until at least this point
- Around 5 December 2026Students expected to be without heating until about this date
Works extended at the Gravas school complex
The Municipality of Athens has pushed back completion of gas network works at the Gravas school complex, which had been set for the end of November. Over 80% of the welds on the large boiler room's piping show no leaks but cannot be certified under current specifications. According to the municipality, those welds date from the network's original installation in 2003.
The deputy mayors for technical services and education, Panagiotis-Paris Charlaftis and Thomas Georgiadis, issued a joint statement on the city's obligations toward the complex's two boiler rooms.
“We have taken on bringing both boiler rooms of the complex into compliance.”
The small boiler room has been reconnected
The smaller boiler room, which serves the 40th Athens Gymnasium, received a fire-resistant door, and its existing trench was covered. A section of the gas piping was also replaced. The ENAON inspection was completed on Friday, 20 November, and the gas supply was switched on. A check sheet has been issued, and the municipality is still waiting for the tightness certificate for that room.
Larger works and the pipe replacement
The large boiler room received a self-contained fire compartment around its boilers, a new fire-suppression network and a rebuilt electrical installation with new light fittings. Radiographic testing that followed led the municipality to replace the whole gas run, from the supply point to the boilers, about 100 metres in length. That work started on Friday, 20 November, and is estimated to take at least 15 days.
“It should be made clear that the first priority of the municipal authority is restoring the smooth and safe operation of the complex's heating system.”
Cost, timing and heating
The total cost of the interventions is 230,000 euros, of which 100,000 euros covers the additional works. The municipality had aimed to finish by the end of November, but work now continues until at least early December. Students at the Gravas complex are expected to stay without heating until around 5 December.
- Total cost of interventions
- 230000 EUR
- Additional works
- 100000 EUR
Data from the article text
Technical findings and wider concerns
A report from the Technical Chamber of Greece (TEE), presented to the Athens municipal education committee by Foti Sourtzis, a regular ELME representative on the body, found that the heating system had not been fully inspected for at least 15 years. The same report recorded deviations from the original study, fire-protection problems and technical faults in welds. Sourtzis also said a 23 November target for restoring heating had passed without the problem being fixed. A Vima report cites 65 metres of gas pipe for replacement, a figure that differs from the roughly 100 metres in the municipal statements, and the two numbers have not been reconciled.
The concerns reach beyond Gravas. The 20th Primary School in Agios Panteleimonas closed for three days after plaster fell, and the building dates from 1895. Georgiadis said the ceilings had swelled and that sections came away after light interventions. The school is expected to reopen on Friday, 27 November, after repairs.
Ask about this text
Sources and context
- H KαθημερινήGravas: Completion of works at the school complex delayedΓκράβα: Καθυστερεί η ολοκλήρωση των εργασιών στο σχολικό συγκρότημα · original in Greek
- NewsITGravas: Students without heating for another 10 days - Works extended, 100 metres of gas pipes being replacedΓκράβα: Χωρίς θέρμανση για ακόμα 10 ημέρες οι μαθητές - Επεκτείνονται οι εργασίες, αλλάζουν100 μέτρα σωληνώσεων φυσικού αερίου · original in Greek
- Η ΝαυτεμπορικήGravas: Over 80% of the large boiler room pipe welds could not be certified todayΓκράβα: Πάνω από το 80% των συγκολλήσεων των σωληνώσεων του μεγάλου λεβητοστασίου δεν μπορούσαν να πιστοποιηθούν σήμερα · original in Greek
- ΣΚΑΪGravas: New works in the boiler roomsΓκράβα: Νέες εργασίες στα λεβητοστάσια · original in Greek
- Places
- Athens
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar