Motru, Romania: over 530 students learn online as the town stays without central heating

Students at the Liceul Tehnologic Motru are learning from home after the town of more than 15,000 lost central heating and hot water. The mayor plans gas mini heating plants for five schools, but the works could take about six months.

AI text based on reports by Libertatea, Ziare.com and G4Media.ro. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Motru · Romania
How it came to this
  1. 31 MarHeating plant permanently closed under the National Recovery and Resilience Plan commitments
  2. 9 NovProject documentation for the five school mini heating plants reaches the relevant staff
  3. 12 NovStudents at the Liceul Tehnologic Motru switch to online lessons
  4. 13 NovTender documentation expected on the tender platform

Classes move online

More than 530 students at the Liceul Tehnologic Motru are attending lessons from home, according to Libertatea, while Ziare.com and G4Media put the figure above 550. The format resembles the remote teaching used during the pandemic. The situation was reported to the Gorj County School Inspectorate, and the arrangement was set for an indefinite period because the school has no alternative heating. Other schools in the town warm their classrooms temporarily with air conditioners or electric heaters. School inspector general Marian Staicu explained why only this school moved online.

“Only the students of the Motru Technological High School went online, because they have no alternative heating equipment of any kind.”

Marian Staicu

A town without heat for months

Motru, a municipality of more than 15,000 residents in Gorj County, has been without central heating and hot water for several months. The supply stopped after the Uzina de Agent Termic și Alimentare cu Apă was permanently closed on 31 March 2026, as one of the commitments under Romania's National Recovery and Resilience Plan. Ziare.com reports that thousands of apartments lack hot water and heating and that public institutions are also cold. Mayor Cosmin Morega said heating in Motru has never started before 15 to 20 November and that parents should be told the plain truth. Several parents voiced their dissatisfaction online about children learning in the cold.

Mini heating plants and the budget

Mayor Cosmin Morega said the city hall is preparing tender documentation for gas-fired mini heating plants in five educational institutions, a project valued at 7.9 million lei. The local budget covers between 5 and 6 million lei, and the city dropped other investments to revise its budget. Project documents reached the relevant staff on Monday, 9 November, and the tender file was expected on the tender platform on Friday, 13 November. Building permits for the concrete platforms that will hold the mini containers have already been issued. Morega said each school gets units sized to its needs, two or three per site or as many as necessary.

“This is a complex job, we have to adapt these mini heating plants to the existing installations.”

Cosmin Morega

Phased works and remaining buildings

Morega said the investment will run over several months and that each school decides for itself how it operates in the meantime. Ziare.com reports the works could take about six months. Lot two, covering the city hall, local police and the multicultural house, is still in the design phase, so those buildings have no heat either. The municipality gave kindergartens and schools priority and left the other institutions for later. Morega defended the pace of the process.

“It is easy to criticise, but harder to do in a fairly short period, because nobody wants to take into account that the budget was approved.”

Cosmin Morega

What comes next

The sequence so far runs from the plant closure on 31 March to the expected tender on Friday, 13 November. The students at the Liceul Tehnologic Motru remain on online lessons under a measure with no end date. The tender is the next formal step, after which the works could take about six months. No source gives a date for when the new heating will start. The key dates are set out below.