Transport · Hamburg
Hamburg's new 3,700-tonne Sternbrücke slides onto the street on 1,088 wheels, heading for final placement Thursday
The 108-metre steel structure was shifted 50 metres sideways onto Max-Brauer-Allee on Wednesday, with a further several-hundred-metre road journey to its final site at the Stresemannstrasse crossing scheduled for Thursday.
AI text based on reports by N-tv, Spiegel Online and ZEIT ONLINE. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
On Wednesday, the new Sternbrücke was moved from its assembly site onto Max-Brauer-Allee using 48 SPMTs with 1,088 wheels, taking roughly 30 minutes.
After the sideways shift, crews scheduled an eight-hour operation to raise the 108-metre-long bridge to its final installation height of six metres above street level.
Deutsche Bahn advanced the several-hundred-metre journey to the Stresemannstrasse crossing by one day; the route includes a balcony with only 40 cm clearance.
The original Sternbrücke handled roughly 900 regional, long-distance and S-Bahn trains per day before its closure; dismantling began on 24 July.
Deutsche Bahn plans to reopen the bridge for train services by the end of August, with installation expected to be complete by the weekend.
- 30 JulBridge transported several hundred metres to final site at Stresemannstrasse crossing
- 31 JulBridge expected to be installed by the weekend
- 31 AugScheduled reopening for rail traffic
The first sideways shift
A 3,700-tonne steel rail bridge completed its first major manoeuvre in Hamburg's Sternschanze district on Wednesday, moving roughly 50 metres sideways from its assembly site onto Max-Brauer-Allee. The operation, watched by several hundred onlookers, took around half an hour and used 48 self-propelled modular transporters (SPMTs) riding on a total of 1,088 wheels, each able to rotate 360 degrees. The road surface had been built up by an average of 60 centimetres and covered with steel plates to distribute the load.
“I am very satisfied and full of joy.”
Deutsche Bahn project lead Janna Widmaier said her team had worked towards the Wednesday and Thursday dates for years. Lars de Haas, project manager for Dutch firm Mammoet which executed the sideways shift, noted the operation finished slightly ahead of schedule.
“We were a bit faster than planned. That gives us more calm for the remaining work.”
Lifting to installation height
Later on Wednesday, the 108-metre-long, 21-metre-wide structure was to be raised hydraulically to a height of six metres above street level, the elevation at which it will ultimately be installed. Widmaier confirmed that eight hours were allocated for the lifting process. The sequence of sideways shift followed by hydraulic lift was designed as a two-stage intermediate step before the bridge travels to its permanent location.
Thursday's road journey through tight spaces
The most delicate phase remains the several-hundred-metre road transport to the final site at the Stresemannstrasse intersection, now brought forward to Thursday. Widmaier told NDR that the route includes very narrow passages, including one point where the bridge must pass a balcony with only 40 centimetres of clearance. The original plan had scheduled the move for one day later, but Deutsche Bahn advanced the timetable. The bridge is expected to be installed by the weekend.
“There are some very tight spots we have to pass through. In daylight it is a bit clearer.”
Why the old bridge is being replaced
The Sternbrücke carries the Verbindungsbahn, a central link in Hamburg's rail network connecting the main station and Altona station. Before the current closure, around 900 regional, long-distance and S-Bahn trains crossed its four tracks daily. After roughly 100 years of service, the steel structure had reached the end of its technical lifespan. Deutsche Bahn cited the condition of the built-in steel and other factors in the decision to replace it. Dismantling of the old railway bridge began on 24 July, and the new bridge is scheduled to reopen for rail traffic on 31 August.
Ask about this text
Sources and context
- Places
- Hamburg
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar