Energy Grid · Brussels

EU deal sets permit deadlines for renewables, grids and charging points

Council and Parliament negotiators reached a provisional deal setting time limits for licensing solar, storage, charging and grid projects, with silence counting as approval at some stages.

AI text based on reports by SAPO, Berliner Zeitung, Notícias ao Minuto and other publishers. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Brussels · Belgium

A provisional deal on the grids package

Negotiators for the Council of the EU, which represents national governments, and the European Parliament reached a provisional agreement in the early hours of 18 November 2026 to speed up approval of renewable energy, power grid and storage projects. The deal revises the directive on permits and forms one of two pieces of a wider grids package, the other being a revision of the regulation on trans-European energy infrastructure (TEN-E). The Council presents the measure as a way to tackle long delays that hold back such infrastructure across Europe and to speed up electrification. The Parliament says the directive should help bring down energy prices. The Commission's proposal dated from December, and both institutions must still confirm the text before it can take effect. Irish minister Darragh O'Brien, whose country holds the rotating Council presidency, backed the aim of cutting reliance on imported fossil fuels.

Fixed deadlines for permits

For the first time, the deal sets deadline limits for licensing grid, standalone storage and charging projects. Solar installations and their associated storage, excluding hydrogen, must be authorised within three months under the new rules. Standalone battery storage and charging points face a six-month limit, while pumped hydro storage can take up to two years. Requests to connect these projects to the grid must be answered within three months, a period that can stretch to six in duly justified cases. Isolated or small systems, such as those in the EU's outermost regions including the Azores and Madeira, receive exceptions. Member states may also rule that a silent authority at intermediate stages counts as approval, and a central online portal or linked portals will handle applications.

Maximum authorisation period by technology under the new rulesmonths
Solar and associated storage
3 months
Standalone batteries and charging points
6 months
Pumped hydro storage (2 years)
24 months

Data from the article text

Thresholds and local benefits

The power threshold that requires authorisation for small-scale solar, storage and charging installations rises from 100 kW to 200 kW. Charging stations with a total installed capacity of one MW or less will need no administrative authorisation at all. The threshold for mandatory sharing of benefits with local energy communities drops from 10 to 7 MW, so municipalities hosting larger renewable plants should benefit appropriately. Member states may give renewables and power grids priority as projects of overriding public interest, with exceptions for security, defence and cultural heritage. The Commission also plans to simplify environmental assessments without weakening nature protection.

Grid bottlenecks and the investment gap

The Commission says building transmission grids in Europe takes more than ten years on average, and more than half of that time goes on licensing. The Commission estimates investment needs for power grids to 2040 at more than one trillion euros. EU energy commissioner Dan Jørgensen said plenty of generated energy is waiting to be connected, but the grids are not yet ready. Tagesspiegel notes that power generated in Denmark often cannot feed into German networks as well as it should, because those networks lack capacity. Some renewable generation has to be curtailed at times because the grids lag behind the build-out of wind and solar.

Concerns and next steps

In June, five European energy associations, among them the Bundesverband der Energie- und Wasserwirtschaft (BDEW), warned that excessive simplification could put grid security at risk. They argued that grid operators must keep checking connections and keep smaller plants in view. The simplified procedures therefore depend on how member states apply the tacit approval option and the exceptions. Formal confirmation by the European Parliament and member states is still pending before the rules can take effect. Until then, the current licensing procedures continue to apply across the bloc.