Unit 1 of the Cernavodă nuclear plant was reconnected to Romania's grid at 01:00 on Saturday, 14 November, restoring nuclear output from both reactors. Nuclear generation was about 983 MW at 12:16 that day, or 16.13% of national production.
AI text based on reports by Stirile ProTV, Mediafax.ro and Digi24. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Unit 1 synchronized with the grid at 01:00 on Saturday, 14 November, and is due to reach nominal power at 07:00 on Sunday, 15 November, according to Transelectrica data.
The two reactors together produced 997 MW against a combined maximum of about 1,400 MW, with Unit 2 at its nominal 700 MW since Thursday, 12 November.
Unit 1 was shut on 28 July and Unit 2 on 13 August as low Danube flow left too little cooling water, leaving Romania without nuclear power for more than three and a half months.
Nuclear supplied about 983 MW, or 16.13% of output, while total production of about 6,085 MW covered 5,973 MW of consumption, leaving a surplus of about 111 MW.
- 11 NovUnit 2 reconnected to the national grid
- 12 NovUnit 2 reaches its nominal 700 MW
- 14 NovUnit 1 synchronized with the national grid
Unit 1 returns to the grid
Romania is producing electricity from both reactors at the Cernavodă nuclear power plant again, after Unit 1 was reconnected to the National Energy System during the night from Friday to Saturday, 14 November. Transelectrica data put the synchronization at 01:00 on Saturday, and output is being raised in steps, with the reactor due to reach nominal power at 07:00 on Sunday, 15 November. An earlier update published on Friday, 13 November, still showed Unit 1 disconnected, with a reconnection estimated for Saturday morning. Unit 2 had been reconnected on Wednesday, 11 November, and reached its nominal 700 MW on Thursday, 12 November. At the time of the latest report, the two reactors together were producing 997 MW, against a combined maximum of about 1,400 MW that could be reached by Sunday evening.
Summer shutdowns and the drought
Unit 1 was taken offline on 28 July because low Danube levels during the drought left too little water to cool the installations. Unit 2 followed on 13 August, and both shutdowns came during the summer's low river flow. Unit 1 then operated for only three days, between 6 and 9 November, before stopping again because of a fault in its non-nuclear section. Nuclearelectrica's director announced changes to the plant's technical management after that fault, including the replacement of the technical director from 1 December 2026. The restart ends a stretch of more than three and a half months in which Romania had no nuclear power.
Midday grid balance
At 12:16 on Saturday, 14 November, nuclear output was about 983 MW, or 16.13% of Romania's total electricity production. Total production stood at about 6,085 MW against domestic consumption of 5,973 MW, a surplus of about 111 MW that let the country export a small amount of power. Natural gas (about 1,503 MW) and wind (about 1,483 MW) were practically level, each supplying roughly a quarter of output. Solar delivered 996 MW, hydro 539 MW, coal 519 MW and biomass 72 MW, while storage was not feeding the grid. Wind, solar, hydro and biomass together supplied about 51% of production, and adding nuclear brings the share of sources with no direct CO2 emissions during generation to roughly two-thirds. Earlier, around 05:00, output had fallen to roughly 4,750-4,800 MW against consumption of 5,300-5,400 MW, and imports covered the gap.
- Natural gas
- 1503 MW
- Wind
- 1483 MW
- Solar
- 996 MW
- Nuclear
- 983 MW
- Hydro
- 539 MW
- Coal
- 519 MW
- Biomass
- 72 MW
Data from the article text
Nine-month picture
A Transelectrica report published on Friday, 13 November, compares January to September 2026 with the same period of 2025. Net domestic consumption fell 3% and net production rose 1%, while exports grew 43% and imports rose only 4%. Thermal sources (gas and coal) fell 3%, nuclear output dropped 31%, hydro rose 10%, and renewables (wind, solar and biomass) grew 31%. Installed thermal capacity fell about 20%, from 5,507 MW on 30 September 2025 to 4,427 MW on 30 September 2026. The net production mix for January to September 2025 was 32% thermal, 25% hydro, 21% nuclear and 19% renewables.
- Thermal
- 32 %
- Hydro
- 25 %
- Nuclear
- 21 %
- Renewables
- 19 %
Data from the article text
Ask about this text
Sources and context
- Stirile ProTVBoth Cernavodă reactors are in operation. How Romania's energy production looksAmbele reactoare de la Cernavodă sunt în funcțiune. Cum arată producția de energie a României · original in Romanian
- Mediafax.roThe Cernavodă plant operates with both units. Reactor 1 has been reconnected and has started delivering energy to the systemCentrala de la Cernavodă operează cu ambele unități. Reactorul 1 a fost reconectat și a început să livreze energie în sistem · original in Romanian
- Digi24Romania is producing energy again with both Cernavodă reactors. What power have they reachedRomânia produce din nou energie cu ambele reactoare de la Cernavodă. Ce putere au atins · original in Romanian
- Mediafax.roRomania's energy production grew in the first nine months, despite the Cernavodă plant shutdown, and exports almost doubled. Who are the new performers and when will Unit 1 be restartedProducția de energie a României a crescut în primele nouă luni, în ciuda opririi centralei de la Cernavodă, iar exporturile aproape s-au dublat. Care sunt noii performeri și când va fi repornită Unitatea 1 · original in Romanian
- Organizations
- Transelectrica
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar