Energy Grid · Cernavodă
Cernavodă Unit 1 nuclear reactor set to reconnect to grid on Friday, 6 November
Nuclearelectrica has begun start-up steps for Unit 1, with resynchronisation to the national grid planned for Friday, 6 November, and full power expected at about 19:00 on Saturday, 7 November.
AI text based on reports by Libertatea, adevarul.ro, HotNews.ro and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Nuclearelectrica expects Unit 1, rated at about 700 MW, to resynchronise with the national grid on Friday, 6 November 2026, with sources giving 11:00 or 13:00 as the start time.
The reactor is expected to reach maximum power around 19:00 on Saturday, 7 November, after which Unit 1 enters normal commercial operation.
Unit 2 restarts only after a sustained rise in the Danube, which was shut down on 13 August, and Energy Minister Dumitru Chisăliță put a realistic restart near 15 November on 27 October.
The government extended special measures to 30 November, allowing Transelectrica to curb large industrial consumers or halt exports, with peak November demand possibly reaching 8,500 MW.
- 6 NovPlanned resynchronisation of Unit 1 with the national grid
- 7 NovUnit 1 expected to reach maximum power
- 30 NovSpecial grid measures extended to this date
Start-up procedures under way
Nuclearelectrica told the Bucharest Stock Exchange on Wednesday, 4 November, that it had begun start-up manoeuvres for Unit 1 of the Cernavodă plant once the minimum conditions for a safe restart were in place. The company described reactor start-up as a complex operation carried out under strict procedures and nuclear security requirements. Resynchronisation with the national energy system is estimated for Friday, 6 November 2026. Unit 1 has an installed capacity of about 700 MW, and Libertatea describes it as the largest individual energy facility in Romania.
“Starting Unit 1's start-up manoeuvres, once the minimum conditions for a fully safe start are met, is an important step.”
Synchronisation and ramp-up schedule
Libertatea gives the grid connection as Friday afternoon, from 11:00, while a Transelectrica timetable reported by adevarul.ro puts the synchronisation at 13:00 on the same day. After synchronisation, power will be raised in stages, with the reactor held at set load levels for fixed periods so that technical parameters can be checked before it runs at full output. The reactor is expected to reach maximum power around 19:00 on Saturday, 7 November. From that point Unit 1 is due to enter normal commercial operation and deliver its full output to the transmission network.
Why the reactors are offline
Both units were taken offline because the Danube's flow dropped so far that safe operation of the plant was threatened. Unit 1 was shut down on 28 July, although Libertatea gives 27 July, and Unit 2 was disconnected from the grid on 13 August, when the whole plant went offline. Nuclearelectrica said at the end of October that both reactors were held in safe shutdown and that the water level in the pump intake basin had risen, though the general rise of the Danube upstream of Cernavodă had not yet followed. A restart requires the level to hold for several days and keep trending upward. Prime Minister Luca Niculescu said the plant could return within days if the recent rain keeps lifting the river flow.
“I hope we will have good news in a few days.”
Speaking to TVR, Niculescu said it was raining, that the flow was starting to improve, and that the restart date would depend on how the river behaves.
Unit 2 and grid pressure
Unit 2 can only restart after a sustained rise in the Danube, because Unit 1's operation draws large volumes of water for cooling and lowers the level in the intake basin. Once that condition is met, Unit 2 will be synchronised to the national grid afterwards. Energy Minister Dumitru Chisăliță said on 27 October that about two weeks was a realistic timeframe for a Cernavodă reactor to restart, which put the date around 15 November. Meanwhile the government has extended until 30 November the special measures that let Transelectrica limit consumption by large industrial users or halt electricity exports if supply security is at risk. Documents behind that extension indicated that peak demand in November could reach 8,500 MW, and could go higher in much colder spells.
Next steps for the operator
Nuclearelectrica says it is working with the competent authorities and partners on short-, medium- and long-term solutions to raise the availability of its installations and reduce the effects of any similar event. Gioară thanked the plant's specialists, who carried out professional and responsible work to keep the units in safe condition throughout the shutdown. He said the company will continue the measures it has already started in case such circumstances recur. Both the company and the prime minister tie the restart to river levels in the coming days, so the timetable depends on whether the current rise in the Danube holds.
Ask about this text
Sources and context
- LibertateaCernavodă Unit 1 to be restarted in two days: how long until it returns to normal operationUnitatea 1 de la Cernavodă va fi repornită peste două zile: cât durează până când revine în ritmul de funcționare normală · original in Romanian
- adevarul.roCernavodă restarts the first reactor. Transelectrica announced the return schedule to the systemCernavodă repornește primul reactor. Transelectrica a anunțat calendarul revenirii în sistem · original in Romanian
- HotNews.roReactor 1 at Cernavodă, in restart procedures. When could it be reconnected to the energy systemReactorul 1 de la Cernavodă, în proceduri pentru repornire. Când ar putea fi reconectat la sistemul energetic · original in Romanian
- Digi24Nuclearelectrica announces the start of start-up manoeuvres for Unit 1 at CernavodăNuclearelectrica anunţă începerea manevrelor de pornire a Unităţii 1 de la Cernavodă · original in Romanian
- Luca Niculescu
- Prime Minister of Romania, who said the plant could restart within days
- Places
- Cernavodă, Romania, Bucharest, United States
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar