Energy Grid · Łeba, Choczewo, and Szczecin
Orlen and Northland Power finish installing 76 turbines at Poland's 1.2 GW Baltic Power offshore wind farm
The Baltic Power offshore wind farm has completed the assembly of its 76 turbines 23 kilometres off the Polish coast, aiming for full 1.2 GW operation to power 1.5 million homes by late 2026.
AI text based on reports by Spider's Web, www.money.pl, wnp.pl and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Crews finished erecting all 76 Vestas V236-15 MW turbines across a 130-square-kilometre offshore area 23 kilometres from the Polish coast.
Orlen chief executive Ireneusz Fąfara confirmed the 1.2 GW installation will reach full generation capacity of up to 4 TWh annually by the end of 2026.
The facility first transmitted power into Poland's national grid on 10 July 2026 via the Choczewo substation when 54 turbines were in place.
Polish firms represent about 21% of lifecycle project spending, with more than one-third of the nacelles produced at Vestas's factory in Szczecin.
- 10 JulFirst electricity feeds into the national grid with 54 turbines installed.
- 7 OctInstallation of all 76 wind turbines is completed.
- Late 2026The wind farm is scheduled to reach full commercial generation capacity.
Offshore installation completed
Crews have completed the assembly of the 76th and final wind turbine at the Baltic Power site in the Polish Baltic Sea. The project is developed jointly by Polish energy group Orlen, which holds a 51% stake, and Canada's Northland Power, with 49%. With all turbines standing, the offshore installation campaign has concluded 15 years after Orlen filed the initial concession application in 2011. Operating at a capacity of 1.2 gigawatts, the facility will generate up to 4 terawatt-hours of electricity annually, meeting about 3% of Poland's national electricity demand and supplying over 1.5 million households.
Orlen chief executive Ireneusz Fąfara addressed the milestone during a press conference on Wednesday.
“76 turbines are installed. This is a great moment, because it also shows that we can build, for the first time in Poland, large investments in industry for which we had no prior experience, that we found great partners with whom we could do this, and that we are ready for next challenges.”
Construction scale and offshore logistics
The Baltic Power farm spans 130 square kilometres, situated roughly 23 kilometres off the Polish coast near Łeba and Choczewo. The installation features 76 Vestas V236-15 MW turbines, each delivering an output of 15 megawatts. Individual blades measure 115 metres, sweeping a rotor area of 43,000 square metres, exceeding the area of six football pitches. Total height reaches over 250 metres above sea level, with foundations anchored up to 100 metres into the seabed.
The offshore campaign deployed approximately 7,000 workers and 110 vessels across an 18-month offshore construction schedule. Specialized jack-up vessels elevated themselves above the sea surface on seabed legs to hoist heavy components in Baltic weather conditions. In addition to the turbines, teams installed two offshore substations and laid hundreds of kilometres of subsea inter-array and export cables.
Testing and grid integration
Electricity generation began prior to final turbine placement. On 10 July 2026, the facility delivered initial power to the national grid via the Choczewo substation in Osieki Lęborskie, when 54 turbines were standing. Turbines are now undergoing grid synchronization and individual 240-hour reliability runs before operational handover.
Jarosław Broda, a board member at Baltic Power, described the operational transition.
“The installation of the last turbine closes the offshore construction phase and opens the phase of commissioning, tests, and technical acceptances. We are checking whether each turbine operates correctly and meets the requirements of the transmission system operator.”
Orlen stated that the entire facility will reach full commercial capacity by the end of 2026.
Domestic supply chain and local manufacturing
Polish suppliers account for approximately 21% of lifecycle spending on Baltic Power, delivering steel structures, cabling, foundation components, and logistics support. More than one-third of the nacelles were manufactured at the Vestas factory in Szczecin, while selected tower sections used recycled steel to decrease turbine carbon footprints. Orlen procurement director Roman Kowszewicz noted that the company established a dedicated team to apply supply chain lessons from Baltic Power to future offshore wind developments.
Northland Power chief executive Christine Healy assessed the completed installation.
“Baltic Power is a breakthrough project for Poland and an excellent example of what can be achieved through strong partnerships. Together with Orlen, we are building a safer and more independent energy future for Poland, creating lasting value for future generations.”
- Orlen
- 51 %
- Northland Power
- 49 %
Data from the article text
Ask about this text
Sources and context
- Spider's WebPolski Bałtyk pełen gigantów. Wyprodukują prąd dla 1,5 mln domów
- www.money.pl"Po raz pierwszy w Polsce". Koniec wielkiej inwestycji. Prąd dla 1,5 mln domów
- wnp.plBaltic Power przetarła wiele szlaków. Orlen już myśli o kolejnych farmach
- Parkiet76 turbin na Bałtyku. Baltic Power zmienia polską energetykę
- Christine Healy
- Chief executive officer and president of Northland Power
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar