Safety · Chlewnica
Fire destroys nearly 90% of ELWOZ-ECO waste plant in Chlewnica, 150 jobs at risk
A fire that broke out on 15 August at the ELWOZ-ECO waste management plant in Chlewnica, Pomeranian voivodeship, destroyed nearly 90% of the facility, including four halls and an office building, with over 200 firefighters mobilised at the peak of the operation.
AI text based on reports by radiogdansk.pl, TVN24, Dziennik Bałtycki and other publishers. Changed . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Four halls totalling about 5,000 m² and an office building were destroyed at the ELWOZ-ECO facility in Chlewnica, Potęgowo municipality, on 15 August.
At the peak on Saturday evening, nearly 60 units with over 200 firefighters from PSP and OSP battled the blaze; by Sunday afternoon 60 firefighters in 30 units remained.
Seven firefighters required medical aid for overheating, treated on site by medical-rescue firefighters; one OSP volunteer twisted an ankle and was taken to hospital.
Mayor Dawid Litwin said losses will be in the tens of millions of zloty and over 100 of the nearly 150 employees may have no workplace to return to.
The Specialist Chemical-Ecological Rescue Group from PSP Gdynia found no toxic emission threat to residents; the municipality still advised keeping windows closed.
- 15 AugFire localized, area and volume no longer increasing
- 16 AugOvernight operations with 5 excavators turning and cooling waste
- 16 Aug60 firefighters remain, fighting external waste heap, buildings extinguished
Outbreak and spread
A fire was detected by facility security at the ELWOZ-ECO waste management plant in Chlewnica, Potęgowo municipality, Słupsk county, on Saturday 15 August at approximately 12:30. The alarm was raised to the State Fire Service immediately. By 15:00, 28 units with roughly 100 firefighters were on scene and three halls were already burning. Reinforcements were called in, and by early evening nearly 60 units with over 200 firefighters from PSP and OSP units across the region were engaged. The fire spread to a fourth hall and the administrative-office building, bringing the total affected area to approximately 5,000 m² across four production-storage halls, plus the office building and significant raw-material storage areas.
Firefighting challenges
The blaze was localised shortly before midnight on Saturday, meaning its area and volume were no longer increasing. Five excavators were deployed to grab waste, turn it so firefighters could douse it thoroughly, and move it to a safe location. Water was drawn from nearby hydrants and a lake close to the plant. Firefighters worked through the night in rotation, with a dedicated rest point for hydration and hot meals. Dense smoke rose several hundred metres, forcing crews to operate in breathing apparatus. Firefighters did not climb the external waste heap due to the risk of hidden voids that could pose a lethal danger.
Captain Piotr Basarab of PSP Słupsk told Radio Gdańsk on Sunday that 30 units with 60 firefighters remained on site, focused on extinguishing the storage-quadrant heap. He said the cause was not yet known and the operation's duration remained uncertain.
Casualties and medical aid
Seven firefighters required medical assistance during the operation. Pomorski PSP commander Jacek Niewęgłowski, who commanded the operation, said the aid was provided on site by firefighter-medics and none of the seven required hospitalisation; they rested under observation. One volunteer firefighter from OSP twisted an ankle while laying a water-supply line and was transported to a hospital emergency department. Niewęgłowski noted the fire service had its own ambulance on site, providing continuous support for hydration, rest, and meals.
Environmental and community impact
The Specialist Chemical-Ecological Rescue Group from PSP Gdyni continuously monitored air quality and found no toxic-emission threat to residents. The municipality of Potęgowo issued an urgent advisory asking residents to close windows and doors and limit time outdoors. There are no residential buildings near the plant, and no civilians were injured. The fire did not spread beyond the facility's grounds, and crews worked to prevent it from reaching a nearby forest.
Economic fallout
Mayor Dawid Litwin, who arrived at the scene within minutes of the alarm and spent over a dozen hours at the command post, estimated losses in the tens of millions of zloty. He said the plant, built and developed over 25 years, was destroyed in a matter of hours.
“It's a terrible day for the municipality of Potęgowo and for over 100 employees. I hope the plant can be rebuilt, but what I saw allows me to say that over 90% of the company has burned down. The losses are enormous.”
The facility employs nearly 150 people, and local authorities began organising assistance for workers who from Monday would have no workplace to return to. Litwin, who has served as mayor for 12 years, said he had never seen a fire of this scale. He thanked PSP and OSP firefighters from Potęgowo and the wider region, as well as residents who supplied drinking water and hot meals to crews throughout the operation. The company, ELWOZ-ECO, issued a statement on Sunday confirming that firefighting in the four buildings was complete and that ongoing work concerned the open-air storage quadrant. The company said it was monitoring the situation and cooperating with all agencies involved in the rescue operation and investigative proceedings.
Ask about this text
Sources and context
- radiogdansk.plPożar w Chlewnicy: wciąż płonie ogromna hałda [AKTUALIZACJA] - Radio Gdańsk
- TVN24Pożar zakładu przetwarzania odpadów. Firma zabrała głos
- Dziennik BałtyckiOgromny pożar zakładu z odpadami komunalnymi w Chlewnicy. Obecnie trwa dogaszanie hal i składowisk
- Nasz DziennikTrwa dogaszanie pożaru Zakładu Gospodarowania Odpadów w Chlewnicy
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar