Transport · Warsaw
Warsaw Wschodnia rebuild starts 17 January 2027, long-distance trains shift to Warsaw Gdańska
Long-distance trains will no longer run between Warsaw Wschodnia and Warsaw Centralna once the station rebuild begins on 17 January 2027, with Warsaw Gdańska taking on much of the through traffic.
AI text based on reports by pb.pl, Życie Warszawy and Nasz Dziennik. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
From 17 January 2027, long-distance trains will not run between Warsaw Wschodnia and Warsaw Centralna, and the section between Warsaw Centralna and Warsaw Antoninów will be closed to traffic.
Trains served daily by Warsaw Gdańska are set to rise from about 195 to about 360 between 17 January and 13 March 2027, according to PKP PLK.
The first stage covers platforms 1 to 4 and the long-distance tracks, the second covers platforms 5 to 7 and the suburban tracks, and the works are expected to finish in 2029.
- 17 JanFirst stage of the Warsaw Wschodnia rebuild starts
- 13 MarEnd of the period in which Warsaw Gdańska is set to handle about 360 trains a day
- Completion expected in 2029Rebuild works at Warsaw Wschodnia expected to be finished
Works start on 17 January 2027
The rebuild of Warsaw Wschodnia station begins with its first stage on 17 January 2027 and is expected to last about two years. Disruption is expected to last at least 21 months in total. While the first stage runs, the section between Warsaw Centralna and Warsaw Antoninów will be closed to traffic, along with selected fragments near Warsaw Wschodnia. The changes apply mainly to long-distance services, which will no longer run between Warsaw Wschodnia and Warsaw Centralna. Railway operators say they will keep a broad offer of regional, suburban and long-distance connections during the works.
Two stages and a 2029 target
Anna Znajewska-Pawluk of the PKP PLK press team explained that the rebuild is split into two stages. The first will modernise platforms 1 to 4 together with the tracks used by long-distance trains. The second stage will cover platforms 5 to 7 and the suburban tracks. Railway operators expect the works to be finished in 2029. Once they are complete, a renovation of the diameter line between Warsaw Zachodnia and Warsaw Stadion is expected to begin.
Warsaw Gdańska takes on the main traffic
Krzysztof Grünke, director of the Centre for Railway Traffic Management at PKP PLK, said Warsaw Gdańska will take over a key role during the rebuild. The station was prepared for higher traffic and, thanks to a new tunnel and earlier investments, can receive almost twice as many trains as it does now. Between 17 January and 13 March 2027, the number of trains served by Warsaw Gdańska is set to rise from about 195 to about 360 a day. The station will handle EIP, EIC, IC and TLK services linking Warsaw with the Tricity, Kołobrzeg, Hel, Olsztyn, Białystok, Rzeszów, Lublin, Kraków, Zakopane, Szczecin, Poznań, Zielona Góra, Wrocław and Jelenia Góra.
- Before 17 January 2027
- 195 trains per day
- 17 January to 13 March 2027
- 360 trains per day
Data from the article text
Regional routes and transfer stops
Koleje Mazowieckie trains will also use Warsaw Gdańska, on routes between Góra Kalwaria and Modlin, Warsaw Zachodnia and Działdowo, Warsaw Gdańska and Radom, and Warsaw Targówek and Skarżysko-Kamienna. Traffic will be spread across Warsaw Gdańska, Warsaw Centralna, Warsaw Wschodnia and Warsaw Główna, plus transfer points including Warsaw Ulrychów and Warsaw Młynów. The distribution is set to keep the wide offer of regional, suburban and long-distance connections running. Operators have announced that this offer will be maintained while the works continue. Warsaw Gdańska is the main station for through traffic, while the other stations take the remaining services.
Timeline ahead
The first stage starts on 17 January 2027, and the increased load at Warsaw Gdańska is planned until 13 March 2027. The second stage, covering platforms 5 to 7 and the suburban tracks, follows the first, with completion expected in 2029. The disruption to rail traffic is set to last at least 21 months from the start of the works. Once the station work is finished, a renovation of the diameter line between Warsaw Zachodnia and Warsaw Stadion is expected to start.
Ask about this text
Sources and context
- pb.pl17 January 2027 modernisation of Warsaw Wschodnia begins. Where will trains be diverted?17 stycznia 2027 r. ruszy modernizacja Warszawy Wschodniej. Gdzie zostaną przekierowane pociągi? · original in Polish
- Życie WarszawyReconstruction of Warsaw Wschodnia begins. Changes in train traffic from 17 JanuaryRusza przebudowa Warszawy Wschodniej. Zmiany w ruchu pociągów od 17 stycznia · original in Polish
- Nasz DziennikCapital: Reconstruction of Warsaw Wschodnia stationStolica: Przebudowa dworca Warszawa Wschodnia · original in Polish
- Places
- Warsaw