Energy Grid · Sierre and Chippis
Valais inquiry: 2024 Rhône flood at Sierre was avoidable, state failed collectively
The Valais parliamentary commission says a 2008 flood protection project, if carried out, would very probably have prevented the June 2024 overflow at Sierre and Chippis. Its report, published on Thursday, 19 November 2026, finds no single culprit but a collective failure of the canton.
AI text based on reports by rts.ch, SRF News, SWI swissinfo.ch and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
An expertise commissioned by the inquiry concludes that the 2008 protection measure, if carried out, would very probably have prevented an overflow at that spot in June 2024.
The commission blames fragmented administration and disputes among cantonal services, including the mobility service, which kept questioning choices validated by the 2016 plan.
Urgent works since the flood only partly improved protection, villas face a collapse risk, and no timetable exists for the Sierre-Chippis section.
The report recommends early coordination, clear decisions and monitoring of execution, and studying a separate entity for operational management of the 162 km third correction.
- 12 DecCantonal parliament sets up the inquiry commission
- February 2025Commission begins its sittings
- 19 NovCommission report published
What the inquiry concluded
On Thursday, 19 November 2026, the Valais parliamentary inquiry commission published its report on the Rhône flood of late June 2024 in Sierre and Chippis. The commission concludes that the damage was avoidable and that the cause was a collective failure of the canton and its administration rather than the fault of one individual. Its president, Damien Revaz, presented the findings at a press conference in Sierre that morning, together with three other members. The river broke its banks and inundated residential districts and industrial zones, and the damage is reported as running into the millions, or tens of millions, of francs.
Revaz summarised the commission's main finding in these words:
“The commission highlights insufficient preparation for a complex file, notably a lack of dialogue with the industries located near the Rhône.”
Between February 2025 and October 2026 the commission met 45 times, gathered about 16,000 documents and held 41 hearings. It also commissioned a technical expertise and a legal opinion from a professor at the University of Fribourg.
- Meetings
- 45
- Hearings
- 41
- Documents collected
- 16000
Data from the article text
A protection project that stalled for 16 years
The priority protection measure for the sector was put out for public inquiry on 11 April 2008. Phase 1 had still not been approved when the flood hit, and it had not been built 16 years later. The cantonal parliament set up the inquiry on 12 December 2024, after the flood. The commission holds that the canton should have been able to overcome the difficulties so that the project did not stall for nearly 20 years.
The commission's expertise concludes that, had the 2008 measure been carried out, an overflow at that spot in June 2024 would very probably not have happened. Urgent works undertaken since then have only partly improved protection, and the situation remains unsatisfactory, notably because adjacent villas risk collapsing. The development plan for the third Rhône correction, adopted in 2016, was meant to end the disputes, yet several cantonal departments, including the mobility service, kept questioning choices already validated. Ministers never settled these disputes, according to the commission.
Collective failure and the human cost
The commission finds no single culprit but a collective failure of the state, with a compartmentalised administration and unresolved turf battles between cantonal services. Vice-president Anne-Laure Secco put the lesson in these terms:
“We do not want to relive a Sierre - Chippis bis.”
The human cost is still visible. Some residents evacuated on the night of 29 to 30 June 2024 have not yet returned home, and the two aluminium works, Novelis and Constellium, needed more than a year to restore their plants. Emergency works carried out after the flood did not secure the site, and no timetable has been set for finishing the protection of the Sierre-Chippis section.
Recommendations for the third Rhône correction
The third Rhône correction covers 162 kilometres of river in Valais and Vaud, is meant to protect about 100,000 people and to prevent damage estimated at 10 billion francs. The project is costed at about 3.6 billion francs, of which 2.1 billion is financed by the Confederation. Some sections are already under construction, such as at Visp, while others, including Gampel and Brig, are not due before 2040.
Among its recommendations, the report calls for a lasting improvement in governance, with early coordination, clear decisions, identified responsibilities and monitoring of implementation. It also recommends studying the transfer of operational project management for the third correction to a separate entity.
- Total estimated cost
- 3.6 billion francs
- Financed by Confederation
- 2.1 billion francs
Data from the article text
Ask about this text
Sources and context
- rts.chRhône flood: Valais' responsibility pointed outCrue du Rhône : la responsabilité du Valais pointée du doigt · original in French
- SRF NewsPUK on Rhône flood: Damage could have been preventedPUK zu Rhone-Flut: Schäden hätte verhindert werden können · original in German
- SWI swissinfo.ch2024 Rhône overflow: Valais state pointed outDébordement du Rhône de 2024: l'Etat du Valais pointé du doigt · original in French
- SWI swissinfo.chInvestigation sees avoidable Rhône flooding in ValaisUntersuchung sieht vermeidbare Rhone-Überschwemmung im Wallis · original in German
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar