Energy & Trade · Austin and Abilene
Texas governor halts new data center grid approvals, orders audit of 474 GW in connection requests
Governor Greg Abbott directed ERCOT and the Public Utility Commission to audit all planned data centers seeking grid connections before any more projects can move forward, citing a queue of 474 gigawatts in proposed demand.
AI text based on reports by engadget, Reuters, Gizmodo and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
ERCOT is reviewing 474 gigawatts of proposed new electricity demand, more than five times the state's record peak load, with about 90% coming from data centers.
Governor Abbott directed PUCT and ERCOT to audit all planned data centers seeking grid connections; projects that fail to comply will be denied.
ERCOT's interconnection queue grew from 233 GW in January to 474 GW by August, driven largely by data center proposals.
At least 335 data centers operate in Texas with 248 more planned, second only to Virginia, with OpenAI's Stargate facility located in Abilene.
A June Reuters/Ipsos poll showed just one-third of Americans approve of data-center construction pace; New York imposed a moratorium last month.
- January 2026ERCOT queue at 233 GW of projects waiting to connect
- June 2026ERCOT approves framework to manage data center power demands
- July 2026New York becomes first state to impose moratorium on large-scale data centers
- 4 AugQueue reaches 474 GW; Abbott orders audit and pauses new approvals
The governor's directive
Texas Governor Greg Abbott on Monday ordered a pause on approvals of new data center projects through the state's grid interconnection process. In a letter to the Public Utility Commission of Texas (PUCT) and grid operator ERCOT, Abbott directed the agencies to conduct a comprehensive audit of all planned data centers seeking connections before any additional facilities are allowed to proceed. The governor's office said ERCOT is currently reviewing more than 474 gigawatts of proposed new electricity demand, more than five times the state's record peak load. Roughly 90% of those requests come from data centers.
“Any data center project that fails to comply with the verification and audit process to protect the reliability and resilience of the Texas electric grid must be denied. Simply put, Texans must come first.”
What developers must disclose
Under the new requirements, developers will have to provide detailed information on expected electricity demand, on-site power generation plans, water consumption and sources, tax incentives or public subsidies received, and ownership structures. They must also explain how they plan to mitigate noise, light pollution, traffic, and other effects on nearby communities. Projects that fail to comply with the requirements set by PUCT and ERCOT, or with state law, will be denied a connection to the grid.
The scale of the queue
The size of ERCOT's interconnection queue has grown dramatically this year. In January, ERCOT had 233 gigawatts of projects waiting to connect to its grid. In less than six months, that figure more than doubled to 474 gigawatts. While many of those proposals are paper projects that may never be built, even a fraction of that demand could place significant pressure on the state's power grid. Texas is already home to at least 335 operating data centers, with at least 248 more planned, making it the second-largest data center market in the country behind Virginia.
Rising opposition and political pressure
Local opposition to data centers has been growing due to their heavy use of energy and water, along with pollution from the power generation needed to run them. A June Reuters/Ipsos poll showed just one-third of Americans approve of the pace of data-center construction. Last month, New York became the first state to impose a moratorium on large-scale data centers. Last week, Texas Lieutenant Governor Dan Patrick joined calls for regulators to deny applications for three 765-kV transmission lines under ERCOT's Permian Basin Reliability Plan, citing objections from rural landowners over the routes.
“If these lines are going to be built, which many believe must be built, then the PUC's transmission approval process must not only prioritize strengthening the grid, but also protect Texas landowners and communities.”
Energy context
Texas has attracted major tech companies including Meta, Amazon, Microsoft, Google, and OpenAI, which are pouring billions into infrastructure for AI models. OpenAI's flagship Stargate data center is located in Abilene. While the state has benefited from ample natural gas reserves and a rapid buildout of wind and solar (utility-scale solar capacity grew fourfold between 2021 and 2025), electricity prices have been rising. Data centers and crypto mining facilities have pushed prices higher, according to the Energy Information Administration. ERCOT said it would postpone a study under a framework approved in June to manage data center power demands while it reviews Abbott's directive.
Ask about this text
Sources and context
- engadgetTexas governor orders audit of new data centers after realizing over 400 gigawatts of power is a lot - Engadget
- ReutersTexas governor orders pause on new data center approvals pending audit
- GizmodoTexas Pauses New Data Center Projects Looking to Connect to the State's Grid
- TechCrunchTexas halts new data centers as governor calls for audits
- Greg Abbott
- Governor of Texas who ordered the audit and pause on new data center grid approvals
- Dan Patrick
- Texas Lieutenant Governor who called for denying applications for three 765-kV transmission lines
- Places
- Austin, United States