Deutsche Telekom doubles AI computing power in Munich with about €250 million
The Industrial AI Cloud in Munich's Tucherpark was fully booked seven months after its February launch. Deutsche Telekom now plans to double the facility's power to 20 megawatts for about €250 million.
AI text based on reports by Handelsblatt, Der Tagesspiegel, stern.de and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Telekom is investing about €250 million to lift the Munich facility's power from 10 to 20 megawatts, adding Nvidia Blackwell Ultra B300 processors.
The Industrial AI Cloud opened in February and was fully booked seven months later, with Siemens and Daimler Truck among its users.
Economy Minister Katherina Reiche (CDU), Digital Minister Karsten Wildberger (CDU) and Bavarian Minister-President Markus Söder (CSU) took part in or endorsed the expansion.
Telekom says the facility uses less than 1.2 kilowatt-hours of power per kilowatt-hour of IT consumption and will heat the whole Tucherpark quarter with waste heat.
- February 2026Industrial AI Cloud opens at the Tucherpark after six months of conversion work
- Seven months after openingThe first stage is fully booked
- May 2026Telekom starts planning further expansion stages
- 9 NovTelekom announces an expansion of about €250 million to 20 megawatts
Expansion after rapid uptake
Deutsche Telekom is expanding its AI data center in Munich's Tucherpark, roughly doubling its computing capacity. The company is investing about €250 million, and the facility's power rises from 10 to 20 megawatts. Officials and executives gathered at the company's Munich innovation center for the announcement on Monday, 9 November, including Economy Minister Katherina Reiche, Digital Minister Karsten Wildberger, Bavarian Minister-President Markus Söder and Siemens CEO Roland Busch. The added servers use Nvidia's Blackwell Ultra B300 processors, which are optimized for training AI models, and RTX Pro 6000 chips will remain in use.
- Before expansion
- 10 MW
- After expansion
- 20 MW
Data from the article text
Demand and the Munich timeline
The first stage of the Industrial AI Cloud is already fully booked, according to Telekom. Among its users are Siemens and Daimler Truck, and Agile Robots, a Munich maker of AI-driven robots, was among the first customers. Ferri Abolhassan, who heads the Telekom subsidiary T-Systems, said on Monday that a well-filled project pipeline points to further demand. The facility went into operation in February after six months of conversion work, and its original investment was one billion euros. Seven months after that opening, the facility was fully booked, which led Telekom to begin planning further expansion stages in May.
Political backing and the US debate
Wildberger used the event to call for determination, saying the following:
“Team No finds reasons, Team Yes finds answers and solutions. Today here in Munich is a strong commitment to Team Yes.”
Reiche argued that the next wave of AI would change how factories produce, and that Germany must combine its long-built industrial expertise with AI. Putting the case for infrastructure in one sentence, she said:
“Computing power is the location factor of our time.”
Reiche also urged that legitimate local concerns about new large facilities should not turn into blanket opposition, citing the recent US midterm elections. There, data center expansion became a campaign issue after residents across party lines protested the electricity and water use of AI facilities, and many municipalities imposed moratoriums or building conditions. Söder praised the project as an investment without public funds and criticized what he called 'Angstkultur' and bureaucratic hurdles, while pointing to Bavaria as a leading site for deep tech and research.
Energy use and open questions
Telekom says the facility needs less than 1.2 kilowatt-hours of electricity, including cooling and other infrastructure, for each kilowatt-hour of IT consumption. The company also plans to use the waste heat to supply the entire Tucherpark quarter. Telekom chief executive Tim Höttges said Germany must not only use AI but create its own value:
“Germany must not only be a user of AI, but must itself create added value and prosperity.”
Telekom is examining a wider expansion of its commitment in Bavaria, but no final decision has been made, and it depends on sound financial conditions. Wildberger also said chips from the Dresden start-up Sparxity should be used in future to strengthen technological sovereignty.
Ask about this text
Sources and context
- HandelsblattArtificial intelligence: Telekom doubles AI computing power in MunichKünstliche Intelligenz: Telekom verdoppelt KI-Rechenleistung in München · original in German
- Der TagesspiegelArtificial intelligence: Telekom doubles AI computing power in MunichKünstliche Intelligenz: Telekom verdoppelt KI-Rechenleistung in München · original in German
- stern.deDemand for AI: Deutsche Telekom expands Munich data centerNachfrage nach KI: Deutsche Telekom baut Münchner Rechenzentrum aus · original in German
- HandelsblattMunich: Telekom invests another quarter billion in AI factoryMünchen: Telekom investiert eine weitere Viertelmilliarde in KI-Fabrik · original in German
- Tim Höttges
- Telekom chief executive
- Karsten Wildberger
- Federal Digital Minister (CDU)
- Katherina Reiche
- Federal Economy Minister (CDU)
- Markus Söder
- Bavarian Minister-President (CSU)
- Roland Busch
- Siemens CEO who attended the announcement
- Organizations
- Siemens
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar