Energy Grid · Paks and Cernavodă
Hungary restarts Paks turbine as Danube rises 19 cm, while Romania's Cernavodă faces new water decline
Hungary reconnected a second turbine at the Paks nuclear plant on 10 August after the Danube rose 19 cm above record lows, while Romania's Cernavodă plant faces renewed water level drops and a possible temporary shutdown of Unit 2.
AI text based on reports by Digi24, Libertatea, adevarul.ro and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
The plant, which normally supplies about half of Hungary's electricity, had been reduced to approximately 10% of capacity with only one of eight turbines running. One turbine produces 225 MW versus the normal 2,000 MW.
The Danube's lowest point was recorded on the night of 4 August 2026 at minus 140 centimetres. In Hungary the river dropped to 23 cm, below the previous record of 33 cm set in 2018.
After barge sinkings raised water 4 cm around Cernavodă's cooling pumps, the Danube dropped 5 cm on 10 August. State Secretary Cristian Bușoi warned Unit 2 may need a temporary shutdown.
The Paks 2 expansion with Rosatom relies on Danube cooling; Magyar said this must be reevaluated and cooling towers may be considered. The government plans to auction 700 MW of wind capacity by 31 August.
Local press reports the Danube needs to rise at least 5 cm more before all four Paks units can be reactivated, a process that could take more than a week if no further drops occur.
- 3 AugRomania detonates Pârjoaia rock to divert Danube flow toward Cernavodă plant
- 4 AugDanube hits record low at minus 140 cm in Hungary
- 7 AugMagyar warns situation remains difficult, urges energy conservation
- 10 AugDanube up 19 cm at Paks; turbine 3 reconnection begins; Cernavodă drops 5 cm
Paks restarts second turbine
Hungary began reconnecting a turbine at the Paks nuclear plant on Monday, 10 August, after the Danube rose 19 centimetres above the record low recorded a week earlier. Prime Minister Péter Magyar announced on Facebook that turbine 3 of unit 2 would start producing electricity by Monday evening. The plant, which normally supplies about half of Hungary's electricity, had been reduced to approximately 10% of capacity, with only one of its eight turbines still running. One turbine generates 225 megawatts, compared with the plant's normal output of 2,000 MW when all reactors are operational.
Last week, Hungary shut down three of the plant's four reactors after Danube water levels fell to record lows, leaving only a single turbine from one reactor in operation. The Danube provides the cooling water essential for the plant's reactors.
Record lows and temporary relief
The Danube's lowest point was recorded on the night of Tuesday, 4 August 2026, when the gauge showed minus 140 centimetres. In August 2026, the Danube in Hungary dropped to 23 centimetres, below the previous record low of 33 centimetres set in 2018. The rise observed on Monday followed rains in Austria, but Magyar cautioned that the increase may be temporary, with no significant additional precipitation anticipated afterward.
Magyar described the situation at Paks as remaining "difficult" and said the government is working on solutions in case low water levels become permanent. He had urged companies and citizens to reduce electricity consumption during evening hours and dimmed decorative lighting on historic buildings in Budapest. On Friday, 7 August, he told a press conference that the Hungarian economy cannot function for months without the nuclear plant.
“We must find a solution for the operation of the Paks nuclear plant, because the Hungarian economy cannot function without this plant for months.”
- Normal (all turbines)
- 2000 MW
- One turbine (reduced)
- 225 MW
Data from the article text
Romania's Cernavodă plant under pressure
Downstream in Romania, the situation at the Cernavodă nuclear plant has worsened. After interventions last week, including the detonation of the Pârjoaia rock on 3 August and the controlled sinking of four barges loaded with stones to create a dam, the water level around the cooling pumps of Unit 2 rose by 4 centimetres, enough for approximately 9 days of operation. However, by Monday the Danube at Cernavodă had dropped 5 centimetres, with forecasts indicating continued decline.
State Secretary Cristian Bușoi said the improvement from the barge sinkings was not durable and warned that Romania must prepare for a scenario in which Unit 2 does not operate for a short period.
“After the first sinkings, we saw an improvement in the Danube level in the Cernavodă area. From the data we have, it seems that this effect was not a lasting one.”
Bușoi said the population would not be affected even if Unit 2 shuts down, as Transelectica could temporarily limit consumption for large industrial companies. He recommended reducing consumption during peak hours, particularly between 19:00 and 22:00. Romania declared a state of energy emergency for the entire month of August.
Long-term questions
The crisis has prompted Budapest to revisit the Paks 2 expansion project, built with Russia's Rosatom. The current design relies on Danube water for cooling, and Magyar said this approach must be reevaluated, with cooling towers among the alternatives being considered. The government also plans to auction 700 MW of wind capacity by 31 August and aims to install 4 GW of wind energy by 2030. According to local press, the Danube needs to rise at least another 5 centimetres before all four Paks units can be reactivated, a process that could take more than a week, provided no further drops occur.
Ask about this text
Sources and context
- Digi24Ungaria reconectează o turbină a centralei nucleare de la Paks. Cu cât a crescut nivelul Dunării
- LibertateaPeter Magyar a anunțat că nivelul Dunării a crescut cu 19 centimetri, iar Ungaria repornește reactorul 2 de la Paks
- adevarul.roPremierul Ungariei anunță că nivelul Dunării a crescut cu 19 cm față de minimul înregistrat săptămâna trecută. Ce se întâmplă la centrala Paks
- Stirile ProTVPéter Magyar anunță că nivelul Dunării a crescut cu 19 centimetri. Câte zile are asigurată apa centrala de la Cernavodă - Știrile ProTV
- Péter Magyar
- Prime Minister of Hungary, announced turbine restart at Paks on Facebook
- Cristian Bușoi
- State Secretary in Romania's Ministry of Energy, warned Cernavodă Unit 2 may need temporary shutdown
- Places
- Cernavodă
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar