Safety · Craiova

Avioane Craiova hands over first two modernised IAR-99 SM trainers, years after deadline

Two of the ten upgraded IAR-99 SM trainers were received in Craiova on 16 November 2026, after a June 2024 delivery deadline was missed. A third aircraft is expected in late November.

AI text based on reports by G4Media.ro, Mediafax.ro, adevarul.ro and other publishers. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Craiova · Romania
How it came to this
  1. 16 NovFirst two IAR-99 SM aircraft received in Craiova
  2. Late November 2026Third aircraft expected, weather permitting
  3. 31 DecDeadline for the remaining seven aircraft

Two aircraft handed over

On Monday, 16 November 2026, Avioane Craiova handed over the first two IAR-99 SM (Standard Modernizat) aircraft to the Romanian Ministry of National Defence (MApN). The ministry said a final reception commission, made up of specialists from the Directorate-General for Armaments (DGA) and the Air Force General Staff, received the two aircraft in Craiova. They belong to a modernisation programme covering ten aircraft, called 'Revitalizarea și modernizarea aeronavelor IAR-99 din dotarea Ministerului Apărării Naționale'.

The programme aims to build advanced training capacity so that pilots can move on to flying F-16 fighters, while keeping a close air support capability in place. The ministry described the IAR-99 SM as the stage where pilots move from propeller-driven turboprop trainers to jet-powered aircraft, an essential step before the F-16. The upgrade updates on-board equipment and avionics so the aircraft can keep training pilots under current requirements.

Contract and delays

The contract was signed on 14 August 2020 between the ministry and Avioane Craiova SA. It covers the upgrade of ten IAR-99 Standard aircraft to the IAR-99 SM configuration and a logistics support package, worth 275 million lei excluding VAT. The aircraft were due for delivery in June 2024. Avioane Craiova attributed the delay to difficulties in obtaining equipment and components. The project also brought penalties of about 3.62 million lei, and in February 2026 the bank guarantee tied to the advance was partially executed.

Contract value and delay penaltiesmillion lei
Contract value (excluding VAT)
275 million lei
Penalties for delays (approx.)
3.62 million lei

Data from the article text

G4Media reported that the aircraft still lack a military capability the contract requires, and it framed the handover as arriving two years after the agreed deadline. The contract therefore remains open on both delivery and scope for the aircraft still to be handed over.

Remaining aircraft and timetable

Union leader Victor Peța said a third aircraft should be handed over by the end of November, depending on weather that allows the necessary test flights. The remaining seven aircraft are due by 31 December 2027, according to the reporting. Peța said the programme had never been interrupted, even though it faced difficulties along the way. Peța also said the reception commission worked on Friday, Saturday and Sunday and finished its work on Monday.

“Today we handed over two aircraft, and by the end of the month we will hand over one more. The programme continues.”

Victor Peța

Union view on the ministry

Peța pointed to a change of approach from the ministry and the DGA, which the union had sought after a long period in which it felt its concerns were not heard. Peța summarised the company's position in a short statement to the press.

“We hoped we would be understood, because until some time ago we were not understood.”

Victor Peța

Two of the ten aircraft are now delivered, and the seven remaining aircraft are due by 31 December 2027.