Business · Taranto, Genoa, and Novi Ligure

Ex Ilva asks to raise furloughed workers to 8,622, nearly double the current 4,450

The request, which reached Taranto unions late on 16 October, would extend the furlough scheme until 28 February 2027 and covers 4,172 more workers than the current authorisation. Taranto carries most of the cuts, following a Milan court order that halted the hot area of the plant.

AI text based on reports by Bloomberg Business, lastampa.it, Il Fatto Quotidiano and other publishers. Changed . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Taranto, Genoa, Novi Ligure, Milan · Italy
How it came to this
  1. 20 OctCassation hearing on the appeals and Labour Ministry meeting
  2. 27 OctTalks scheduled at Palazzo Chigi
  3. 28 FebRequested furlough period ends unless extended or renewed

The request

Acciaierie d'Italia in amministrazione straordinaria, the former Ilva steelmaker, has asked to raise its furloughed workforce from 4,450 to a maximum of 8,622. The request runs until 28 February 2027, unless it is extended or renewed. The company says 8,622 is the maximum average of simultaneous suspensions, not the number of people who will be out at any one time. Another 1,004 staff would stay on duty to guard assets, meet administrative and environmental obligations and keep operations running. The communication was sent to unions, the Labour and Enterprises ministries and the regions concerned.

Where the furloughs would fall

Taranto carries most of the request, with up to 6,964 of its 7,875 workers. Genoa would see up to 870 of 917 employees, Novi Ligure 515 of 542 and Milan 117 of 125, while Racconigi, Marghera, Paderno and Legnaro account for 70, 45, 23 and 18 workers. AGI gives the Milan base as 127 employees, so that figure differs slightly between reports. The 9,626 total is the figure in the communication, which AGI dates to 30 July. Taranto already has about 3,500 workers in furlough, under an authorisation of up to 3,800 within the 4,450 total.

Maximum furlough requests by siteworkers
Taranto
6964 workers
Genoa
870 workers
Novi Ligure
515 workers
Milan
117 workers
Racconigi
70 workers
Marghera
45 workers
Paderno
23 workers
Legnaro
18 workers

Data from the article text

The court order behind the request

The request follows a decree of the Court of Appeal of Milan dated 27 July, which ordered production in the hot area of the Taranto plant to stop. Appeals by Acciaierie d'Italia and Ilva in amministrazione straordinaria against that decree are set for a hearing at the Court of Cassation on 20 October. In a communication to the ministry, commissioners Giovanni Fiori, Giancarlo Quaranta and Davide Tabarelli wrote:

“The non-deferrable compliance with the court order is currently incompatible with the company's layout.”

Acciaierie d'Italia commissioners

Since 9 October, the suspension of the lines producing slabs and coils has forced a remodelling of company structures that cannot be postponed, with knock-on effects at the other plants. The company has also cancelled raw-material supply orders that no longer fit the shutdown. Plants have been kept in a standby state the company calls 'riscaldo', to prevent deterioration and allow a restart if the legal obstacles are lifted.

Unions push back

Loris Scarpa, national steel coordinator for Fiom-Cgil, called the request a provocation. He said the unions received the new filing late on 16 October, with numbers nearly doubled, as a five-day strike at the plant and its contractor sector was ending. In a note he said:

“Unacceptable both in substance and in timing, given the upcoming meetings and deadlines.”

Loris Scarpa

Scarpa also tied the unions' rejection of furloughs to the explosion of Altoforno 1 in May 2025, saying they have not accepted their use since then. A meeting at the Labour Ministry on 20 October will discuss extraordinary measures for workers and changes to the Council of Ministers decree of 14 October, followed by talks at Palazzo Chigi on 27 October. On the afternoon of 17 October, the Taranto network 'Onda del futuro', which calls for the closure of the steel complex, scheduled a demonstration in the city.

Key dates

The sequence starts with the Milan decree of 27 July and continues with the 9 October suspension of the slab and coil lines. The unions plan to seek changes to the 14 October Council of Ministers decree at the 20 October ministry meeting, the same day as the Cassation hearing. Talks at Palazzo Chigi follow on 27 October. The requested furlough period ends on 28 February 2027 unless it is extended or renewed.