Elbtower builder Lupp starts dismantling cranes to pressure Hamburg
Construction firm Lupp has begun removing equipment from Hamburg's unfinished Elbtower as negotiations with the city stall. Two cranes are due down by Friday, 20 November, while a third special crane stays on the site.
AI text based on reports by Süddeutsche Zeitung, N-tv and Norddeutscher Rundfunk. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
Lupp began removing equipment on 19 November. Its authorised signatory Marcus Eckert said two cranes and about 250 tonnes of material would be removed by Friday, 20 November.
dpa reports two cranes coming down with a third special crane left standing, while NDR describes one of the two high-rise cranes being dismantled.
Hamburg has offered the consortium, which includes Lupp, 595 million euros to buy part of the tower. Mayor Peter Tschentscher said the city would not be pressured.
Lupp halted the build in October 2023, citing unpaid payments. The Signa company Elbtower Immobilien GmbH & Co. KG then filed for insolvency at the Berlin-Charlottenburg local court.
- October 2023Lupp halts work on the tower, citing unpaid payments
- 9 NovFAZ report carries Thilo Moser's demand that the city move
- 19 NovLupp begins removing equipment from the site
- 20 NovPlanned deadline for removing two cranes and their material
Equipment removal begins
Lupp, a construction firm from Nidda in Hesse, has started removing equipment from the unfinished Elbtower in Hamburg, as it had announced in advance. The work began on Thursday, 19 November. Lupp authorised signatory Marcus Eckert told reporters at a media event on the site that workers would dismantle two cranes and remove concrete distribution devices by Friday, 20 November. He put the total material to be taken away at about 250 tonnes, and a third special crane will remain standing on the tower for now. NDR reported that one of the two high-rise cranes is to come down and that the firm had brought in a mobile crane, equipped with its own specialist gear such as climbing equipment, for the job. The two accounts differ on how many cranes are involved, and the figure of two comes from the dpa report.
Why the tower has stood idle
The Elbtower has been an unfinished high-rise for more than three years. It belongs to the insolvent Signa group, founded by real estate investor René Benko, who has since been convicted. Lupp stopped work in October 2023, citing payments that were due but had not been made. The Signa company Elbtower Immobilien GmbH & Co. KG then filed for insolvency at the Berlin-Charlottenburg local court. Hamburg is now negotiating with a consortium that wants to finish the building, and Lupp, which is responsible for the tower's shell construction, is part of that group. The city has offered the consortium 595 million euros to buy part of the tower, where a natural history museum is to be housed.
Lupp's pressure on the city
Lupp says talks with the city are taking too long, and NDR reports that the negotiations have stalled. In a report published on 9 November by the Frankfurter Allgemeine Zeitung, technical managing director Thilo Moser addressed the city directly:
“City of Hamburg, get moving! Otherwise we're out of here.”
Hamburg's mayor, Peter Tschentscher (SPD), told RTL Nord afterwards that the city would not allow itself to be pressured. NDR reports that the removal is meant to increase pressure on the Hamburg Senate, and that the firm planned a press conference on Thursday morning to explain the procedure. The reporting describes the talks with the consortium as still ongoing.
Key dates
Work on the tower stopped in October 2023, and the insolvency filing followed. Moser's remarks reached the public through the 9 November report in the Frankfurter Allgemeine Zeitung. Dismantling started on 19 November, and the two cranes and their material are due to be removed by Friday, 20 November.
Once the two cranes are down, one special crane remains on the tower for now. No date for resuming construction has been set in the reporting.
Ask about this text
Sources and context
- Süddeutsche ZeitungElbtower construction firm Lupp removes equipmentElbtower-Baufirma Lupp transportiert Gerät ab · original in German
- N-tvHamburg & Schleswig-Holstein: Elbtower construction firm Lupp removes equipmentHamburg & Schleswig-Holstein: Elbtower-Baufirma Lupp transportiert Gerät ab · original in German
- Norddeutscher RundfunkHamburg Elbtower: Construction firm apparently begins dismantling craneHamburger Elbtower: Baufirma beginnt offenbar mit Kran-Abbau · original in German
- Peter Tschentscher
- Mayor of Hamburg who said the city would not be pressured
- René Benko
- Real estate investor whose Signa group owns the unfinished Elbtower and who has since been convicted