Energy Grid · Bucharest

CET București Vest restarts after spring fires, with hot water still depending on Termoenergetica network

ELCEN reconnected the CET București Vest plant to the National Energy System on Sunday, 15 November 2026, about six months after fires in April and May halted it. Hot water and heat for consumers still depend on the municipal network run by Termoenergetica.

AI text based on reports by Digi24, Ziare.com and Mediafax.ro. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Bucharest · Romania
How it came to this
  1. Spring 2026 (April-May)Fires damage electrical equipment and halt the plant
  2. Summer 2026ELCEN commits to restarting the plant on 15 November
  3. 15 NovPlant is returned to operation and reconnected to the National Energy System

Plant back in service

Electrocentrale București (ELCEN) returned CET București Vest to operation on Sunday, 15 November 2026, and reconnected it to the National Energy System. The plant had been shut down since fires in April and May 2026 damaged its equipment, so the restart came roughly six months after the outage began. ELCEN said the date matched the commitment it had made in summer 2026 to start the plant on 15 November. The plant now delivers thermal energy up to the property boundary, the plant's fence. That delivery is only the first step, because the heat still has to be taken over and distributed by the city network before it reaches homes.

“CET București Vest has been returned to operation in full safety, with the connection to the National Energy System successfully completed.”

ELCEN

What the fires damaged

The fires hit electrical equipment central to the plant's operation. According to ELCEN, the damaged components included parts of two 6 kV electrical stations, the 0.4 kV switchgear serving hot water boilers 1 and 2, and power transformers. Some of this equipment was more than 30 to 50 years old: the transformers date from 1994-1995, while the electrical stations were built in 1972-1975 and modernised in the 2000s. ELCEN said the work needed for a safe restart included repairing and installing a power transformer and buying a new one to serve as backup for general plant services. The company stated that such work would normally take about one and a half years, but it was completed in six months.

“Returning the plant to service after major damage from the spring fires was an engineering and logistical challenge without precedent.”

ELCEN

Restoring every affected installation did not end with the restart. ELCEN says the remaining work continues at a steady pace and will be finished by the end of the year. The company describes the repairs as a broader programme than the emergency work that made the restart possible, which means the plant is operating while parts of its rebuild are still under way.

Heat still depends on the city network

During the outage, CET Grozăvești covered the full thermal demand of the plant's customers, ELCEN said, and heat supply was never interrupted. Now the heat must be taken over and carried through the municipal network, which belongs to the city of Bucharest and is run by Termoenergetica. For that reason, ELCEN said, the restart does not automatically mean every connected home will have hot water and heating at normal parameters. The company pointed to the condition of that network and to the extensive construction sites in the capital as factors in delivery. It also cited losses in the network and debts of the heat operator, while saying it is running investments of around five billion lei.

Outlook for the heating season

ELCEN said it is treating each stage of the 2026-2027 heating season with close attention and puts the energy security of the capital and the national system first. The company also reiterated that it is open to institutional dialogue and cooperation with the authorities. Its statements make clear that the plant's output and the homes it serves are two separate tests, with the second relying on the network's performance. Work on the remaining installations is due to finish by the end of 2026, according to ELCEN.