In brief

  • Anthropic committed $35 billion over six years to Lambda for access to a 350-megawatt data center built by Hut 8 in Nueces County, Texas.

  • The deal follows a $45 billion contract with Nscale in West Virginia, along with agreements with Fluidstack ($50 billion), SpaceX ($45 billion), and Amazon (over $100 billion).

  • Anthropic increased its annualized revenue run rate to over $65 billion by late July 2026, up from $47 billion in May 2026 and $9 billion at the end of 2025.

  • Nvidia holds the lease for the Texas facility, following chief executive Jensen Huang's 10 August 2026 financial alliance aiming to assemble over $500 billion for client purchases.

Nueces County
Nueces County, San Francisco · United States
How it came to this
  1. April 2026Anthropic reports service capacity limits during peak hours
  2. May 2026Private funding round values the company at 965 billion dollars
  3. 10 AugNvidia forms financial alliance targeting 500 billion dollars
  4. 31 AugAnthropic agrees to 35 billion dollar Lambda compute deal

Texas data center agreement

Anthropic has agreed to a $35 billion cloud computing contract with Lambda to secure processing power for its artificial intelligence systems. The six-year agreement covers access to a data center facility under construction in Nueces County, Texas. Infrastructure firm Hut 8, a former bitcoin mining enterprise, is developing the site with an estimated power capacity of roughly 350 megawatts. Lambda will deploy Nvidia hardware across the site to support Anthropic's operations, while Nvidia holds the lease for the facility. The agreement provides compute capacity for the Claude model family and developer tools including Claude Code, which assists software engineers with writing and editing code. Neither Anthropic nor Lambda has officially published the terms of the private transaction.

Multi-billion infrastructure expansion

The Lambda commitment follows several large compute agreements finalized by the San Francisco-based developer in recent months. Anthropic recently agreed to a six-year, $45 billion contract with British provider Nscale for 460 megawatts of capacity at a campus in West Virginia, utilizing Nvidia Vera Rubin systems. Additional cloud computing contracts include a $50 billion agreement with Fluidstack, a $45 billion arrangement with SpaceX, a $10 billion deal with a week-old cloud startup, and a $9.1 billion 20-year commitment with bitcoin miner Riot Platforms. Amazon has separately indicated that Anthropic will spend more than $100 billion on AWS over the next decade for five gigawatts of capacity and Trainium3 silicon, alongside a separate hardware package involving Google and Broadcom. Together, Anthropic's disclosed infrastructure commitments exceed $130 billion as the company contracts with specialized neocloud providers focused on high-density graphics processing unit clusters.

Anthropic cloud and compute infrastructure commitments$B
Fluidstack50
Nscale45
SpaceX45
Lambda35
Riot Platforms9.1
Fluidstack
50 $B
Nscale
45 $B
SpaceX
45 $B
Lambda
35 $B
Riot Platforms
9.1 $B

Data from the article text

Financial growth and market valuation

The rapid buildout of processing capacity occurs as Anthropic experiences steep commercial expansion ahead of a planned autumn initial public offering. The company increased its annualized revenue run rate to more than $65 billion by late July 2026, rising from $47 billion in May 2026 and roughly $9 billion at the close of 2025. Anthropic projects its annual revenue will reach between $190 billion and $200 billion by 2028. A private funding round in May 2026 valued the company at $965 billion, more than double its $380 billion valuation recorded in February 2026. The surge in computing demand follows disclosures in April 2026 that high traffic had forced Anthropic to degrade service levels during peak operational hours to manage server load.

Hardware supply and financing structures

The transaction reflects Nvidia's central position across computing hardware, facility leasing, and customer capital. In the Texas arrangement, Nvidia acts as an investor in Lambda, maintains a direct arrangement with site developer Hut 8, and supplies the processing units deployed in the facility. On 10 August 2026, Nvidia chief executive Jensen Huang formed an alliance with six North American financial institutions seeking to assemble more than $500 billion to finance computing infrastructure purchases. Nvidia also introduced a customer revenue-sharing initiative in July 2026, which was paused in late August due to internal antitrust reviews. Anthropic continues to explore further capacity options, including early discussions to lease $10 billion in computing power from Meta.

Next in today’s edition

Zacharia reportedly out as White House press secretary

On Friday, 16 October, Donald Trump said he had urged Katie Zacharia to reconsider her role, while the New York Times reported she had been fired. Her debut briefing had lasted about 14 minutes and followed questions about her legal credentials.

  • Safety · 16 h agoOregon elementary shooting leaves four dead, attacker killed by bystander
  • Business · 17 h agoTesla shows flying Roadster, production targeted for 2028
  • Health & Education · 18 h agoPope Leo XIV recovers from lung surgery, Angelus planned Sunday

Sources and context

  • Il Messaggeroon 1 Sep at 23:53Anthropic, maxi-accordo da 35 miliardi con Lambda per potenziare il cloud IA
  • LesEchos.fron 1 Sep at 16:54Des chèques de 30, 40, 100 milliards de dollars... Avant l'IPO, Anthropic multiplie les deals pour donner de la puissance de calcul à Claude
  • L'Opinionon 1 Sep at 15:59Data centers : le grand quitte ou double d'Anthropic et Open AI
  • ANSA.iton 1 Sep at 12:42Anthropic firma accordo da 35 miliardi con Lambda, supportata da Nvidia - Notizie
Jensen Huang
Nvidia chief executive who formed a financing alliance to fund computing infrastructure purchases

Pollar is free and carries no ads in the text. Its members keep it going.

Support Pollar

Published on 2 Sep at 00:07.

Report an error in the text

Text generated by AI from the reports of the publishers listed and checked automatically, with no human editor. How Pollar is made

In this text

Texas data center agreementTexas data center agreementMulti-billion infrastructure expansionMulti-billion infrastructure expansionFinancial growth and market valuationFinancial growth and market valuationHardware supply and financing structuresHardware supply and financing structures

Based on reports by

Il Messaggero, LesEchos.fr, L'Opinion, ANSA.it, BFMTV, N-tv, The Next Web, Le Figaro.fr

List of sources

AI & Tech · Nueces County and San Francisco

Anthropic signs 35 billion dollar cloud contract with Lambda for Texas data center

The six-year agreement secures roughly 350 megawatts of capacity at a facility built by Hut 8 in Nueces County, expanding infrastructure for the Claude model family ahead of a planned autumn initial public offering.

Nueces County