Transport · Adamuz, Montoro, and Urda

Adamuz rail crash: reports point to 1990 track and Adif welds a month after Urda

Guardia Civil and court experts found 1990-era ballast, sleepers and rails at the derailment point, while AITAT flagged faulty welds. Andalusia still has no date for reopening its rail link.

AI text based on reports by ABC TU DIARIO EN ESPAÑOL, eldiario.es, El Periódico and other publishers. Published . How it is made

For membersThe first 30 seconds for everyone. Synthetic voice (AI).

In brief

Adamuz, Montoro, Urda, Madrid · Spain
How it came to this
  1. 23 NovGuardia Civil report on track materials at Adamuz is dated
  2. 29 NovGeneral election (29N)
  3. 28 DecJudicial secrecy in the Urda case is set to end

Two crashes, one investigation

Ten months after the Adamuz derailment in Córdoba, official reports point to the state of the track and to Adif, the state-owned company that manages it. On 18 January 2026 at 19:43, an Iryo train running from Málaga to Madrid derailed, and three of its cars (6, 7 and 8) crossed onto the neighbouring track. Nine seconds later an Alvia service bound for Huelva ran into the derailed carriages. The crash killed 46 people. El Mundo reports 152 injured, while Europa Press puts the figure at more than 150.

A second disaster followed on a Wednesday in October near Urda (Toledo). An AVE 2080 carrying 397 people struck an Iryo 6076 with 147 passengers at 08:54, after Adif's control centre had let both trains run in normal mode despite a failure of the LZB safety system. El Periódico reports 69 dead and more than 200 injured. El Mundo says both tragedies have shaped the campaign ahead of the 29 November general election.

What the Guardia Civil and court experts found

The Guardia Civil's report, dated 23 November and sent to judge Cristina Pastor in Montoro, examines a stretch between kilometres 316 and 320 on track 1. Most of the 4,000 metres of ballast analysed dates from 1990, with smaller sections from 2025 and 2023. Sleepers and rails follow the same pattern. At the derailment point, a 256-metre rail section from 2025 was joined to a 1,319-metre section from 1990.

“At the specific point of the derailment and its immediate surroundings, the ballast dated from 1990.”

Guardia Civil

Whether the age of the ballast affected the rail break is still pending the experts' report. Court experts told investigators that the age of any material always contributes to a loss of performance, for example in geometry or resistance. AITAT investigators found several welds outside the permitted geometric range in 2025 renovation works, and said supervisors misapplied Adif's safety management system. According to El Mundo, a 6.4 millimetre dip was repaired, reappeared late last year and was not fixed before the crash. Adif recorded 950 rail breaks across its network between 2020 and 2026, 47 of them on high-speed lines over the past decade.

Ballast on track 1 at Adamuz km 316-320, by year laidmetres
1990 (original)
3631 metres
2025 (new)
332 metres
2023 (recycled)
37 metres

Data from the article text

Safety systems, blame and the Urda inquiry

Former transport minister Óscar Puente told Congress that the LZB system had failed 170 times this year up to 30 October, 13 of them on the stretch involved. El Periódico reports that 75% of those failures had causes outside the system itself, such as cable theft or damage. The government pointed from the outset to 'human error' in communications between the control centre and both drivers. The AVE had stopped 25 kilometres behind the Iryo. Puente has resigned, and first vice-president Carlos Cuerpo has taken over the ministry and replaced the heads of Adif and Renfe. The judicial investigation stays secret until 28 December.

Andalusia still cut off by rail

For about a month the rail link between Andalusia and the rest of Spain has been broken, and neither Adif nor Renfe has set a reopening date. A special plan Renfe announced after Urda was suspended before it started, and a second activation was postponed hours after staff were notified. The regional government led by Juanma Moreno is demanding a timetable, safety guarantees and a full audit of rail infrastructure. The Orgaz court authorised Adif to begin rebuilding the track on 19 November, and Puente had told Congress the link could return ten days after that approval. Next week's bridge holiday, with four days off, is expected to bring many travellers.

Monthly train circulation on the Adamuz stretchtrains per month
2023
2512 trains per month
2024
3126 trains per month
2025
3552 trains per month

Data from the article text