Transport · Iași
Romania issues order to start design work for 45 km of A8 motorway, construction eyed for mid-2027
Romania's road infrastructure company CNIR has issued the order to begin the design phase for two sections of the A8 Union Motorway totalling 45 km, with official design work starting on 24 August and heavy machinery expected on site by summer 2027.
AI text based on reports by Libertatea, Digi24, Stirile ProTV and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
CNIR issued the start order on 12 June 2026 but the official design period will not begin until 24 August, allowing time for performance bonds, supervisor appointments and document handovers.
The engineering design stage will run for 10 months from late August 2026, ending in June 2027, which authorities say sets up an immediate start of construction in the dry summer season.
Lot 1 (Moțca–Târgu Frumos, 27 km) and Lot 3 (Lețcani–DN24 Iași, ~18 km) require dozens of bridges, viaducts and tunnels. A 5.5 km priority segment on Lot 1 will connect to the A7 motorway within 12 months.
Contracts were signed about two weeks ago with builders from Romania and Spain, financed through the European SAFE programme.
- 12 JunCNIR issues order to begin design for 45 km of A8
- 24 AugOfficial start of the 10-month design period
- 30 JunDesign phase expected to conclude; construction to begin
The National Road Investment Company (CNIR) issued the start order on 12 June for sections 1 and 3 of the A8 motorway between Moțca and Ungheni, financed through the European Union's SAFE programme. The 45 kilometres of highway, split into two technically demanding lots, will now move through a 10-month design stage before construction gets underway in favourable weather.
Timeline from order to construction
Although the order was signed on 12 June, the actual design work will not start until 24 August. That two-and-a-half-month gap is required under public procurement law: builders must first submit a performance bond and supervising engineers need to be appointed, and all existing documentation (feasibility study, environmental permits, topographical surveys) handed over. Once the design phase officially begins, engineers will have 10 months to complete technical plans, pushing the finish to late June 2027. CNIR director general Gabriel Budescu said the schedule was set so that "after the 10 months allocated to the design phase, actual works will begin in June 2027, right in the favourable construction season." By that calendar, heavy equipment will be mobilised in early summer 2027, bypassing wet spring months that could slow earthworks.
“I issued the order today for starting the design of 45 kilometres of the A8 with SAFE funding. These are two lots with high technical complexity, with many structures, bridges, viaducts and tunnels, and after the 10-month design period, actual works will begin in June 2027, in the favourable construction season.”
Two sections with dense engineering
Lot 1 runs 27 km from Moțca (Târgu Neamț) to Târgu Frumos and contains 36 bridges and viaducts, four tunnels and three interchanges at Moțca, Pașcani and Târgu Frumos. A top-priority 5.5 km segment will be built within 12 months to connect the Leghin–Târgu Neamț section of the A8 and the A7 Moldova Motorway on the Bacău–Pașcani axis. Lot 3 spans nearly 18 km between Lețcani and DN24 (Iași) with 18 passages, six tunnels and two interchanges at the junctions with county road DJ 282 and national road DN24.
Financing and contractors
Both contracts were signed roughly two weeks before the start order and are funded by the EU's SAFE programme. The builders are consortiums of Romanian and Spanish companies, though the articles do not name the individual firms. Secretary of state in the transport ministry Horațiu Cosma described the contracts as signed "only two weeks ago and carried out by constructors from Romania and Spain."
“The new road company CNIR has issued the order to start designing lots 1 and 3 of the Moțca–Iași–Ungheni Motorway, and 24 August has been set as the date for the actual start of the design stage. The two contracts, financed through the SAFE Programme, were signed only two weeks ago and are being carried out by constructors from Romania and Spain.”
Remaining lots await contract awards
The Moțca–Iași–Ungheni corridor includes two further lots, numbered 2 and 4. The transport ministry said it is waiting for the National Council for Solving Complaints (CNSC) to finalise procedures before contracts can be signed for those sections. No timeline was given for when that might happen.
“Step by step, kilometre by kilometre, the Union Motorway A8 takes shape. A strategic project for Moldova and for the whole of Romania, which brings communities closer, creates opportunities and better links the historical provinces of the country. The Union Motorway is no longer just a project on paper. Every day it becomes a reality ever closer to millions of Romanians.”
Ask about this text
Sources and context
- LibertateaStart pe Autostrada Unirii - A8: De ce începe proiectarea celor 45 km abia în august și când intră utilajele în teren
- Digi24Se dă startul la proiectarea tronsoanelor 1 și 3 ale Autostrăzii Moţca - Iaşi - Ungheni. Când s-ar putea intra în faza de execuție
- Stirile ProTVSe construiesc încă 45 de kilometri de autostradă spre ieșirea din țară. "Un proiect strategic pentru întreaga Românie" - Știrile ProTV
- adevarul.roAutostrada Unirii A8 înaintează: 45 de kilometri de drum de mare viteză intră în faza de proiectare pe sectorul Moțca-Iași-Ungheni
- Gabriel Budescu
- Director general of Romania's National Road Investment Company (CNIR)
- Horațiu Cosma
- Secretary of state in Romania's Ministry of Transport and Infrastructure
- Places
- Iași
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar