Privacy, by architecture.

Pollar runs on our own servers in the EU, no US cloud. Analytics are self-hosted and cookieless (Umami). We set no advertising cookies. We load no third-party trackers. Built to WCAG 2.1 AA, works for everyone. AI-supported, human-edited. The AI personalising your feed also runs in the EU.

Privacy & data sovereignty
Pollar
HomeAskLiveSearchMapMarketsNotificationsFor You
BriefThreadsMarkets

Today’s Brief

Hormuz opens, France boils

Congress rebukes Trump as heatwaves close France and markets question AI spending

The past half-day brought a familiar mix of hard power and fragile systems. Washington argued over war authority, Europe sweated through record heat, railways and aircraft faced technical alarms, and investors discovered that AI enthusiasm can reverse quickly.

Read the Brief

Live now

All live coverage
  • Israel bombs Hezbollah targets in Beirut

    Declares the peace protocol a "declaration of defeat of America" as Tehran reacts to the US ratifying the 14-point agreement to reopen the Strait of Hormuz.

  • Nottingham NHS maternity review

    Expands Martha's Rule to all maternity units nationwide following the systemic failures identified in the Nottingham review.

  • France detects first Ebola case

    Exhibited mild symptoms during his return flight, health officials confirm, as the doctor remains in strict isolation following his humanitarian mission in the DRC.

In the spotlight

All threads

World · Updated 1h ago

The US under Trump: second term

The Trump administration's private warnings to EU capitals about new tariffs linked to defence spending and migration represent a continuation of existing pressure tactics rather than a new policy direction.

HomeBriefThreadsAsk
Categories
AI-generated·Learn how
© Wirtschafts Woche
Transport·1h ago

Deutsche Bahn pushes Stuttgart 21 opening to end of 2031, adding five more years of construction

The long-delayed Stuttgart 21 rail project will not open until the end of 2031, Deutsche Bahn told the Bundestag transport committee, pushing the start date five years beyond the already postponed 2026 target.

The new timeline

Deutsche Bahn has officially postponed the opening of the Stuttgart 21 underground through station to the end of 2031, Bahn representatives told the Bundestag transport committee on 24 June 2026. The delay adds five years to a project that was originally scheduled to open in 2019 when the financing agreement was signed in 2009. Construction began in 2010, and the opening date has been pushed back repeatedly. The most recent target, a partial opening in December 2026, was cancelled in November 2025 after digitalisation problems surfaced. Bahn chief Evelyn Palla then ordered a comprehensive review, and the 2031 date is the result.

The problems have shaken me.

— Evelyn Palla

Why the delay

Bahn representatives cited several technical hurdles during the committee session. The digitalisation of the Stuttgart rail node, the first fully digitalised node in Germany, has proved far more challenging than expected. Planning processes lacked the necessary maturity, and media reports indicate that cables must be partially relaid. A technical building is no longer suitable for current requirements, and both control technology and the power supply need reworking. A new emergency power concept is also required.

Impact on passengers

Passengers in Stuttgart will face another five years of provisional arrangements. Long detours around the central construction site to reach long-distance platforms will continue, although a shortcut across the roof of the new station should open from 2027. Frequent line closures, replacement bus services and train cancellations will persist. The Gäubahn link to Zurich must be severed a few months before the new station opens, but the planned Pfaffensteigtunnel via the airport is now scheduled for December 2033, shortening the interruption compared with earlier plans. The S-Bahn extension with the new Mittnachtstraße stop is expected in 2032.

Cost overruns

The 2009 financing agreement capped the distribution of costs at just over 4.5 billion euros. The most recent official estimate stood at around 11.3 billion euros, and the five-year delay is expected to push that figure significantly higher. A court ruling requires Deutsche Bahn to bear all additional costs alone.

Stuttgart 21: key milestones and delays
  1. 2009Financing agreement signed, opening planned for 2019
  2. 2010Construction begins
  3. 2022Wendlingen-Ulm high-speed line opens
  4. 2025-11Partial opening for December 2026 cancelled; comprehensive review launched
  5. 2031-12New target opening for the underground through station
  6. 2033-12Pfaffensteigtunnel planned to open, reconnecting the Gäubahn via the airport

A fully digital rail node

Stuttgart 21 is the centrepiece of the Stuttgart-Ulm rail project, which also includes the Wendlingen-Ulm high-speed line that opened in 2022. The new underground station will replace the existing terminus with a through station, and the entire node will be equipped exclusively with the digital ETCS train control system. Classic light signals will not be installed anywhere in the Stuttgart node.

Stuttgart
Evelyn Palla
Stuttgart

8 sources

  • Weiter Warten auf Stuttgart 21: Bahn verschiebt Eröffnung
    DIE WELT·1h ago
  • Start erst 2031: Weiter Warten auf Stuttgart 21: Bahn verschiebt Eröffnung
    ZEIT ONLINE·2h ago
  • Stuttgart 21: Deutsche Bahn plant nun mit Eröffnung im Dezember 2031
    Süddeutsche Zeitung·2h ago
  • Deutsche Bahn verschiebt Start von Stuttgart 21 auf Ende 2031
    watson.ch/·3h ago
  • Bahnprojekt: Kreise: Bahn verschiebt Stuttgart 21-Start auf Ende 2031
    Handelsblatt·4h ago
  • Bahnprojekt: Kreise: Bahn verschiebt Stuttgart 21-Start auf Ende 2031
    Wirtschafts Woche·4h ago
  • Kreise: Bahn verschiebt Stuttgart-21-Start auf Ende 2031
    Süddeutsche Zeitung·4h ago
  • Kreise: Bahn verschiebt Stuttgart 21-Start auf Ende 2031
    Süddeutsche Zeitung·4h ago

Get Pollar Weekly

The week in news, every Friday. Free.

Free. No tracking, no ads. Unsubscribe anytime.

More from Society & Science
Health & Education·38m ago

France confirms first Ebola case on its soil in doctor returning from Congo

A doctor returning from a humanitarian mission in the Democratic Republic of Congo has tested positive for Ebola in France, marking the first case ever diagnosed on French territory. The patient is stable and isolated, and authorities have launched contact tracing.

© SAPO
Read article
Transport·From Jun 23·Upd. 3h ago

Germany's entire rail network halted by GSM-R radio failure, services resume after two-hour standstill

A nationwide failure of the digital GSM-R railway radio system brought all train traffic in Germany to a standstill on Tuesday evening, stranding thousands of passengers before services resumed around two hours later.

© ANSA.it
Read article
Climate·From Jun 24·Upd. 2h ago

Record heatwave scorches Europe: France hits 44.3C, UK issues red alert, Ireland nears all-time record

A blistering heatwave has shattered temperature records across western Europe, leaving tens of thousands without power in France and prompting the UK's second-ever red heat health warning.

© Al Jazeera Online
Read article