Transport · Florence
Florence rail junction reopens after first phase of Ponte al Pino works, new stop from July 26
High-speed and regional services through Florence's Campo di Marte junction resumed at 4 a.m. on July 10 after a week-long interruption to remove the Ponte al Pino overpass. Another closure, from late July 26 to July 30, will allow installation of the new 550-tonne bridge.
AI text based on reports by Fanpage, Il Fatto Quotidiano, ANSA.it and other publishers. Published . How it is made
For membersThe first 30 seconds for everyone. Synthetic voice (AI).
In brief
High-speed and regional rail services through Florence's Campo di Marte junction restarted on schedule early Friday morning after a week-long closure.
The three-section steel bridge was lifted away by one of the largest cranes used for such a job in Europe, operated by a crew of about 70 specialists.
During the works Rome–Milan high-speed trains faced delays of up to two and a half hours, cancellations and diversions, while regional services were heavily disrupted.
A new stoppage, lasting from 11 p.m. on 26 July to 11 a.m. on 30 July, will allow installation of the 550-tonne replacement bridge and complete the safety-upgrade project.
- 10 JulFirst phase ends; rail traffic resumes after removal of old bridge deck
- 26 JulSecond phase begins with line closure for installation of new overpass
- 30 JulWorks expected to conclude; new 550-tonne Ponte al Pino bridge positioned
Traffic resumes after week-long closure
Rail traffic on the Florence Campo di Marte–Firenze Rifredi and Florence Campo di Marte–Firenze Santa Maria Novella routes resumed at 4 a.m. on Friday, July 10, marking the end of the first phase of the Ponte al Pino overpass replacement. The reopening followed a week of severe disruption that effectively split Italy's main high-speed line between Rome and Milan, forcing long-distance trains onto slower alternative routes and triggering widespread cancellations.
“Nel corso dell'interruzione è stata completata la rimozione del vecchio impalcato, sezionato in tre conci e movimentato con una gru da 2.000 tonnellate, tra le più grandi impiegate in Europa per questo tipo di interventi.”
The work: a complex engineering operation
The old metal bridge deck, which sits above the tracks in a heavily urbanised part of Florence, was cut into three sections and lifted away by one of the largest cranes ever deployed for a rail project in Europe, rated at 2,000 tonnes. Simultaneously, demolition of the existing abutments began, preparing the site for the new structure. About 70 highly specialised workers from leading Italian construction and exceptional-lifting firms took part in an operation that RFI described as one of the most complex engineering feats on the national rail network.
“Le attività, eseguite in un contesto fortemente urbanizzato, rappresentano una delle operazioni di ingegneria più complesse sulla rete ferroviaria nazionale.”
Impact on travel and passenger support
During the closure, long-distance trains faced delays of up to 180 minutes, while regional services were cancelled or rerouted. The alternative route along the old Tyrrhenian line itself suffered faults that further extended journey times. In response, RFI and Trenitalia deployed a dedicated service plan with substitute buses, constant traffic monitoring, and a passenger-assistance operation involving FS Group staff at affected stations and support from the Civil Protection system. The works were planned well in advance with the involvement of the Ministry of Transport (led by Matteo Salvini), the Municipality of Florence and the Tuscany Region.
“I collegamenti sono stati garantiti attraverso un piano di esercizio dedicato, con servizi sostitutivi, itinerari alternativi e un costante monitoraggio della circolazione.”
Second closure set for July 26–30
The next and final work window is scheduled from 11 p.m. on Sunday, July 26, until 11 a.m. on Thursday, July 30. During that period the new Ponte al Pino overpass, measuring 32 metres long, 16 metres wide and weighing approximately 550 tonnes, will be positioned, completing a strategic intervention to renew and strengthen the infrastructure's safety.
Ask about this text
Sources and context
- FanpageRipartiti i treni sulla linea Alta velocità dopo i lavori su Ponte al Pino ma è già programmato un nuovo stop
- Il Fatto QuotidianoTreni Firenze, riapertura tratte dopo lavori Ponte al Pino: cantiere dal 26 al 30 luglio | Il Fatto Quotidiano.it
- ANSA.itRfi, ripresa la circolazione ferroviaria nel nodo di Firenze - Notizie
- Il Sole 24 ORERfi: ripresa la circolazione ferroviaria nel nodo di Firenze
- Matteo Salvini
- Italian Minister of Transport, involved in planning coordination for the Ponte al Pino works
- Places
- Florence
Pollar is free and carries no ads in the text. Its members keep it going.
Support Pollar